Assessing
Biomass Feasibility
|
|
|
 |
Log Book
Week 1
- Literature Review; boiler technology, international
markets, current combustion technologies, exisiting projects, biomass
fuel sources.
- Met with BIB Cochran and Barony College.
- Visit to Barony College.
Week 2
- Literature Review; boiler technology, current
combustion technologies, anaerobic digestion, supply potential,
biomass fuel sources.
- Quantify Demand.
- Barony State of Play.
- Austria and Sweden Case Studies.
- Produced project proposals and project deliverables
(work plan).
Week 3
- Literature Review; Combined Heat and Power
Technologies (CHP), boiler technology, anaerobic digester.
- Meeting with Ron Hill of North Lanarkshire
Council.
Week 4
- Literature Review; funding, anaerobic digester.
- Degree Day and Educational Building energy
consumption calculations.
- Barony College Visit.
- Methodology ideas.
Week 5
- Continuation of literature review.
- Meeting with Margaret Watson from Scottish
Enterprise in Dumfries.
- Barony College energy demand calculations.
- Website design.
Week 6
- Course on wood fuel at Buccleuch Energy in
Selkirk.
- Continuation of literature review.
Week 7
- Biomass CHP investigation.
- Demand reduction methods.
Week 8
- Legislation for anaerobic digester and combustion
technologies.
Week 9
- Cumbernauld case study.
- Cost analysis
- Environmental impact assessment.
- Location of Biomass installation.
Week 10
Week 11
- Website.
- Integration of all the work.
Week 12
- Website.
- Integration of all the work.
Week 13
- Website.
- Conclusions and Acknowledgements.
Week 14
|
|
|
|
|
|