| 
			As it was described 
			in the Methodology part of the Project Web Page, once the demand of 
			the Xscape site is  reduced, the analysis of the supply side 
			can be undertaken. This way a total energy efficiency analysis  
			for construction villages 
			can be performed.  
			 
			In this part of 
			this project an evaluation of the supply side is conducted 
			in order to improve the efficiency of the supply as well as reducing CO2 emissions. 
			  
			In addition, the 
			use of efficient supply options such as Combined Heat and Power (CHP) 
			systems and Heat Pumps as well as renewable supply technologies has been studied. 
			  
Back to Top 
			The objectives of this study are to evaluate  
			alternative supply options for construction villages especially 
			focusing on Laing O'Rourke's Xscape site.  
			  
			 The alternatives have been studied by considering 
			different aspects of construction villages and 
			evaluating the advantages and disadvantages of the different supply options in terms of economic, social and 
			environmental issues. In addition renewable supply technology that 
			is most suitable for construction sites shall be identified and 
			studied in more detail.   
			 
			The study on Laing O'Rourke's Xscape site will be undertaken by considering the 
			current supply options: diesel generator and connection to the grid; 
			as well as the identified renewable solution. 
			   
Back to Top 
			 For the evaluation of the supply side, the actual situation 
			of the supply is analysed using the Xscape site as reference in this 
			project. The following assumptions have been made for our analysis. 
				
				
				The power 
				output will be calculated by using the actual consumption 
				records (metering data) and applying the identified demand 
				reductions.
				
				The demand reduction 
				is estimated according to the Demand Side study of this Project.
				 
			  
			The topics studied have been: 
				
				
				Actual kWh 
				consumption
				
				Reduction by 
				using Demand measures
				
				Future kWh 
				consumption
				
				Evaluation of 
				the actual supply: Diesel generator, connection to the grid.
				
				Evaluation of 
				efficiency for : CHP and Heat Pumps system.
				
				Evaluation of 
				Renewable options. RE selection.
				
				The efficiency 
				results: combination of the supply systems.   
			The methodology to evaluate the supply side is shown in the 
			above flow chart.    
			                                     
			   
			  
			  
			  
			  
			  
			 
			  
Back to Top 
			The energy 
			consumption profile for each construction site varies continuously 
			and generally increases as a project progresses.  The usual 
			practice of considering the annual energy demand is wholly 
			inappropriate for the construction business as projects varies in 
			both time and size.  
			  
			In most 
			construction sites Diesel generators acts as a major source for 
			electricity supply, and thereby constitute to about 75 to 80 % of 
			the fuel costs. For the remaining one third of the project electricity 
			is used from the grid. It is important to note that the 
			carbon emissions resulting from electricity generation by diesel 
			generator are about twice those of mains electricity.   
			Electricity is used for space and water 
			heating, lighting and 
			electrical offices and catering equipment. A deep analysis of the energy use and the power installed 
			can be followed at the demand side analysis of this web site. 
			  
			The profile of the supply is as following. 
			      
			A)  
			In 
			terms of used devices: 
			The electricity required is obtained from a diesel generator 
			and directly from the grid through a grid connection. 
			  
			      
			B)  
			In terms of costs: 
			Following the figures we have obtained from Laing 
			O’Rourke, it can be  estimated that the average expenditure in energy 
			(diesel and electricity) from a typical construction site could be 
			about £126,000 per year. Note that depending on every 
			company and every provider contract prices for fuel and electricity 
			from the grid could be different. 
			 
			  
			Although data for electricity consumption were obtained 
			for the Xscape 
			site those values can not be shown on this web site for 
			privacy reasons. Due to this the average value are assumed as the 
			energy expenditure on the Xscape site. 
			            
			-         
			
			The diesel generator contributes to 88.16% of the 
			total cost of energy supply. 
			            
			-         
			
			The electricity from the grid is about the 11.83% remained. 
			  
			      
			C)  
			In terms of time: 
			Along the project 
			duration the supply of a construction village is 
			
			typically 
			structured into the following periods. 
			            
			-         
			
			2/3 parts of the project:  supply by 
			diesel generators. 
			            
			-         
			
			1/3 parts of the project: grid connection. 
			  
			  
Back to Top 
			On almost all the construction villages, there is a 
			possibility to use temporary power supply from the grid. In order to connect to the grid some considerations must be 
			followed: 
				
				-         
				
				The dates 
				and other key programme dates 
				-         
				
				The location 
				of existing supply lines 
				-         
				
				Local and 
				seasonal environmental considerations 
				-         
				
				The 
				evaluation of the existing supply companies 
				-         
				
				The 
				evaluation of the different quotations, contracts and security 
				of supply from every company. 
				-         
				
				The 
				definition of the supply voltages required. 
				-         
				
				The earthing 
				requirements and proximity to communications equipment 
				-         
				
				The siting 
				and protection of metering, switchgear, distribution boards etc 
				-         
				
				The correct 
				rating of fuses and switchgear for safety and plant protection
				 
				-         
				
				The 
				arrangements for controlling, operating and maintaining the 
				system 
				-         
				
				The 
				provision of lockable switches and means of isolation 
				-         
				
				The 
				commissioning and handover arrangements   
				-         
				
				Future 
				modifications or extensions to the temporary supply system  
			 
			Using some information obtained from experienced civil 
			engineers as well as referring to the Site Layout part of this web 
			site, it can be said that grid connection is not made until roughly 
			two thirds of the project is 
			because of the need to keep the electrical supply options flexible. 
			Temporary facilities are often moved around on site and diesel 
			generators are ideal for shunting around with the facilities. 
			Although ideally they should not be moved as this costs money and is 
			inefficient, it usually happens because of external uncontrolled 
			conditions and/or sometimes poorly planning. Furthermore, the connection 
			into the grid is delayed in order to reduce the risk of accidents by 
			damaging the electricity connections during the buildings 
			activities. 
			  
			It is estimated that it takes between two to four weeks to get a 
			high capacity connection to the national grid. The electricity 
			from the grid is purchased at 7-8 p/kWh. 
			   
Back to Top 
			 As it has been 
			shown in previous chapters of this report, power for the Xscape site 
			at the time of this study was provided mainly by a diesel 
			generator. The diesel generator supplied 66% of the electricity over 
			the whole project duration which incurred 80% of the total 
			electricity costs.  
			  
			On the Xscape, a 200kVA generator is used to provide 
			electricity for lighting, space and water heating, office and catering 
			equipment in the site accommodation. A 27kVA generator is used 
			to supply electricity primarily for temporary lighting with some 
			subcontractors using this generator for their power tools.   
			  
			Diesel 
			generators are the preferred 
			supply 
			systems on 
			sites mainly due to flexibility reasons as well as the ease of 
			obtaining the fuel supply. Nevertheless, some 
			problems are detected regarding diesel generators. 
			  
			Every company has a different contract for their oil price but an 
			average of 20p/litre is considered as a good approximation of a 
			fixed oil price. Thus, at 35% maximum 
			generator 
			efficiency, the price of the diesel is estimated at 5.76 p/kWh. 
			However 
			the price of fuel varies in huge ranges and can be said to 
			increase significantly in the near future.  
			  
			The efficiency of the generator is an important aspect to be 
			considered. The efficiency shows the relationship between the energy 
			use and the total power output from the generator. 
			On of the main problem is that diesel generators are mostly 
			operated only on part of their load. Following the curve shown in the 
			following figure, 
			the efficiency of a diesel generator is strongly related to the 
			load. Thus, with decreasing generator load the efficiency is 
			reducing accordingly. On the Xscape site the load of the generator is fixed at the 
			35.5% what means an efficiency of the 30%.  
			  
			The lower the efficiency of the diesel 
			generator the higher is the amount of CO2 emitted by the 
			generator. Hence, at a load of 35.5% the 
			CO2 emissions from the generator are 0.72 kg/ kWh, which 
			means almost a 70% of 
			increase with respect to the standard of 0.43kg/kWh 
			CO2 applying to the 
			national grid.   
			Thus, electricity 
			produced by the generator is not more expensive than the electricity 
			purchased from the grid, the associated CO2 emissions are 
			extensively higher. This 
			shows that an alternative must be developed to reduce the CO2 
			emissions by improving the generator efficiency or by reducing the 
			generator use. 
			   
 |