Core Two

The Case Study (proposed University building for the Rottenrow site)

 

In 2002 the demolition of the old Rottenrow maternity hospital sited across from the James Weir engineering building at the University of Strathclyde in Glasgow was completed. The site is now currently lying empty. At the time of writing there are plans for the construction of gardens on site, these gardens may not be permanent. There is some discussion of construction of a new building which will act as a meeting point for student in the top floor café, a large open area to use laptops (plug and play), the building may also act as a hub for the university from which there will be easy access to all other university buildings.

 

Several students from the architecture department at Strathclyde (Integrated Building Design) as well as Dr. Howieson from the Architecture Department produced some architectural drawings during the first semester 2002/2003 for a proposed building based on this building concept. Our team was briefed on the concept at the beginning of February 2003. The initial idea was to design a building which was a low energy use building which would act as an example of low energy architecture and also maintained excellent levels of human comfort.

 

Building Concept/Remit

After some discussion with the members of the design team from the architecture department it was decided to go with the initial building concept. There were many aspects of the design which were not yet finalised thus our team made some decisions regarding the function of the building, area and rooms within the building as well as the occupancy regimes and other factors critical to the design.

 

The following areas were decided upon.

 

 

This case study shall act as a working example of the total integrated building design methodology which was constructed by our team during core one of our project.

The primary objective was to use the methodology to determine the renewable and passive technologies, which would be suited to reducing the energy consumption from the grid and fossil fuels technologies towards reducing the emission of CO2 during the use phase of the building. The methodology was to be worked through stage by stage.

 

The planned outcome was to show that the methodology helped in the integration of the most suitable technologies from the very first stage of the building design and would help reduce the time required for the elimination of those technologies which were not suitable for inclusion within the building.

 

Following the Methodology

First stage

The first stage of the methodology involves the determination of the building concept and the production of the draught architectural drawings. The fist stage in the methodology states that architects, integrated building energy system designers and any other designers working on the building should converse at an early stage. In this case the rough architectural drawings were produced by the architecture department during the first semester. Our team was thus unable to take part in the production of the rough architectural drawings.  The building concept or remit had already been stated.  The draught architectural drawings are shown below.

 

The number of occupants had been stated to be around 300 maximum.

 

Stage Two

The most interesting consideration for this site is the slope on which the building is to be constructed, the slope is estimated to be around 20 degrees at points. It can be seen that the draught architectural drawings show that the building is designed with a sloping roof of around 20 degrees south. It should also be stated that there are some tall buildings directly south of the building which could result in some shading of the building. Due to the very short time frame in which this project was to be complete there was no time to conduct a survey of the site. Therefore it was decided in terms of analysis of renewable technology zero shading would be assumed. It was also assumed that as the building would not be considered for construction for at least five years there would be limited significance in reviewing those issues associated with planning permission.

 

Stage Three

The various zones or areas within the building have also been defined in the concept/remit section. All the most vital areas in the building have been designed. There are some area within the building which have not been included in the project remit, these area include toilets which would have a limited effect of the electrical use within the building. The toilets have been considered with respect to the use of water by the occupants. The main electrical equipment contained with the building for the main area is as follows.

 

Plug and play area – 50 laptops (60KW)

 

Café – 4 fridges of 500W, other kitchen electrical equipment is estimated to be around 4KW at peak times.

 

It should be stated that this estimation of the electrical equipment is on the conservative side. There would likely be other electrical equipment such as lighting control (if appropriate), monitors for security purposes and radios. It is estimated that

 

Stage Four

The average internal room temperature (20°C) of and airflow rates (0.5 Air Changes per Hour) were based upon guidelines from the CIBSE guide.

 

Stage Five

The number of occupants has been stated to be a maximum of 300. The following regimes were decided upon for the most important areas i.e. those area with the largest floor areas with in the building.

 

 

Plug and play area

cafe

Exhibition area

Term time, winter

 

 

 

Weekday

09 – 17 = 100% peak occupancy

 

17 – 22 = 40% peak occupancy

09 -17 =100% of peak occupancy

 

17 – 22 = closed

09 – 17 = 100% of peak occupancy

Weekend

09 – 17 = 40% peak occupancy

 

17 – 22 closed

closed

Closed

Periods of immediately prior and after to term time

 

 

 

Weekday

09 – 17 = 75% peak occupancy

 

17 – 22 = 20% peak occupancy

09 -17 =75% of peak occupancy

 

17 – 22 = closed

09 -17 = 75% of peak occupancy

 

17 – 22 = closed

Weekend

09 – 17 = 25% peak occupancy

 

17 – 22 closed

09 -17 = 25% of peak occupancy

 

17 – 22 = closed

Closed

Holiday period (mid summer)

 

 

 

weekday

09 – 17 = 25% peak occupancy

 

17 – 22 closed

09 -17 = 25% of peak occupancy

 

17 – 22 = closed

Closed

weekend

09 – 17 = 10% peak occupancy

 

17 – 22 closed

09 -17 = 10% of peak occupancy

 

17 – 22 = closed

Closed

 

Stage Six 

This stage involves the static heat calculations for the entire building.

The equation Q = U A ∆T is used, the flowing table details the values obtained for The static heat load calculations are based upon the temperature difference between outside and inside for the Glasgow climate.

 

Day of Month

Average Daily Temperature C

Delta T

C

Heat Loss (with roof U-value of 0.2)

kW

Heat Loss (with Glazing on roof U-value 1.8)

kW

January 8th

-3.4

23.4

108.8

179

January 16th

1.3

18.7

89.55

143.1

February 8th

2.7

17.3

82.08

132.4

February 23rd

5

15

71.45

114.8

March 3rd

6.7

13.3

63.26

101.8

March 20th

7

13

61.4

99.47

April 10th

6.6

13.4

63.29

102.5

April 25th

9

11

51.95

88.3

May 5th

11

9

42.51

72.31

May 16th

14

6

29.12

51.07

June 10th

17

3

14.17

28.12

June 29th

19

1

4.72

11.09

July 18th

21

-

-

-

July 31st

21

-

-

-

August 9th

19

1

4.72

11.09

August 24th

18

2

9.47

17.02

September 8th

13

7

33.06

53.56

September 21st

12

8

37.78

59.49

October 1st

11

9

42.51

72.31

October 19th

10

10

47.23

76.51

November 3rd

7

13

61.4

99.47

November 25th

4

16

75.57

122.4

December 6th

8

12

56.68

103.5

December 18th

3

17

80.29

128.4

 

There is a large variation in the space heating loads for the building between the winter and the summer period; this would be expected of most buildings in colder climates such as those in northern latitude countries.

 

Stage Seven - Calculation of the hot water demand

The hot water demand is calculated as follows.

Peak occupancy = 300

Daily use of water per person = 5 litres

Tin = 10

Tout = 43

∆T = 33°C

Heat capacity of water = 4.2 KJ/KgoC

Peak daily consumption from hot water use = (300 * 5 * 33 * 4.2)/3600 = 57.75 KWhr

 

The following table shows the demand for hot water throughout the year

 

period

Hot water demand (KWhr)

Weekdays (06/01 to 02/06)

57.75

Weekdays (22/09 to 31/12)

57.75

Weekend 1 (04/01 to 07/06)

50% peak demand = 28.875

Weekend 2 (20/09 to 27/12)

50% peak demand = 28.875

Weekend 3 (07/06 to 20/09)

50% * 25% peak demand     = 5.775

Holiday period 1 (01/01 to 04/01)

0

Holiday period 2 (01/06 to 20/09)

= 14 .4375

 

Stage Eight - Determine the electrical loads within the building.

It is critical that the equipment required for the various areas within the building is properly defined prior to this stage. The electrical demand was calculated as follows:

 

A lighting value of 8 W/m2 was selected based around 60% of the guideline value of BIBSE. This guideline value is based upon the minimum illumination required. This was reduced as it was concluded that through the installation of energy efficient lighting this value could be reduced substantially.

Thus the maximum lighting load is estimated to be 3000 m2 * 8 W/m2 which equals 24 KW.

 

One of the primary conceptual ideas of this proposed building is the plug and play areas where students can plug in their laptops and have access to other machines such as scanners and printers. Since the majority of electrical demand in this area would be derived from the use of laptops, the electrical demand from appliances within this plug and play area was calculated based upon the estimated peak number of laptops. It is estimated that during peak period there would be approximately 50 laptops in use, most laptops are rated at around 60W thus 50 * 60 equals a peak electrical use from laptops at 3KW.

 

There will also be significant demand from the use of electrical equipment contained with in the café. It was estimated that the café would require 4 refrigerators which are rated at around 500W, this equated to a demand of 2KW. It is estimated that other electrical appliances such as kettles and whisks would require around 4KW of electricity during peak periods.

 

As the university is not occupied 100% of the time there will be a reduced electrical demand over much as the year.

The peak electrical demand is calculated to be 24KW + 6KW + 3KW which equal 33KW.

 

The following was then assumed for the various demand periods. It should be noted that the demand from the electrical side will not match to exactly the reduced occupancy side.

 

= 40% of laptops in use

= 20% of lighting demand

This equates to an electrical demand of approximately 11KW

 

= 90% of electrical demand

This equates to an electrical demand of around 30KW

 

=75 % of Peak electrical demand

This equates to an electrical demand of around 25KW

 

=30% of peak electrical demand

This equates to a demand of around 10KW

 

=30 % of peak electrical demand

This equates to a demand of around 10KW

 

Stage Six – The high level Elimination Tools

High Level Tool for Renewable Technology

§         CHP is ruled out at this stage as it does not match those criteria which are necessary for CHP to act as an effective environmental and economic strategy. This is due to the variation in the heating requirements for the building and an electrical demand regime which is not consistent. It is stated in the selection tool that a CHP plant need to be run at maximum capacity for as much time as is possible. This would not be an effective strategy for the Rottenrow site; thus CHP is eliminated.

§         Small or micro hydro can also be eliminated at this stage. The electrical demand from the building would not warrant construction of a hydro facility as the supply would be in considerable excess to the demand. In some case there may be a partnership between several businesses or residential bodies, in other cases a hydro facility could supply the electricity for to several university buildings. In this case such a partnership does is not possible.

§         The efficiency of the fuel cell system which only provides electricity is considerably less than for a system incorporating cogeneration, where both the electricity and heat produced from the fuel cell are used within the building. In the table it is stated that the ratio of heat to electrical energy produced from the fuel cell is quite high. The Rottenrow building has been shown to have a heating demand profile which varies considerably throughout the year as does the hot water demand. This would mean that during the summer periods of the year the fuel cell would be operating on an electricity producing cycle only. This would mean that the overall yearly efficiency of the fuel cell system would be reduced. This in its self would not necessarily rule out fuel cells from further consideration in the other categories which are driving the design of integrated renewable technology for the Rottenrow building.

 

 

 

The remaining technologies are thus BIPV, Solar Collectors, Ducted Wind Turbines and GHP. Each of these technologies shall be subject to further investigation in the quantitative analysis section.

 

Stage Seven

Detailed Analysis for the renewable technologies deemed suitable for integration into the building by the high-level selection tool

 

The strategy

The first stage in the detailed analysis of the renewable technologies viable for integration into the proposed Rottenrow building involves the study of the demand and supply matching capabilities of each technology. A strategy for carrying out the supply and demand analysis for the various technologies was carried out. The strategy is presented below

 

DETAILED ANALYSIS WITH MERIT