Studying
the current scheme of transmission and distribution networks we
can notice the increasing levels ofdistributed generation(embedded generation).This is occur
because of the ongoing usage of distributed generation with CHP
andrenewable sources and
also the advantages that distributed generation offers.
In
our projectwe triedto study the transmission of renewable energy
in co-ordination with distributed generation and we focusedin a case study in order to deriveuseful conclusions about the economical,environmental
and social feasibility ofusing distributed generation for the transmission of renewable energy.
Distributed generation
can be defined as power generation that is connected directly to
the distribution network instead of the transmission electricity
grid
And also
Not centrally planned(by the utility)
Not centrally despatched
Normally smaller than 30-50 MW
This is a typical figure for distributed generation
,where we can see the connection of the generator not to the transmission
grid but directly to the distribution substation
Distributed generation can be used for various
purposes and by that we mean
for meeting minimum
constant loads as a base load
As a
stand-by for meeting peak loads
and finally
in order to Avoid reinforcement of transmission and distribution
network by picking a strategic location for our distributed generation
Currently
in Scotland there is installed capacity from distributed generation
about 1771 (one thousand seven hundred and seventy one MW)and is expected to reach
2250-2500
MW by the year 2005.
In
this Pie Chart we have the percentage for both centrally dispatched
and distributed generation in Scotland.
Although
the continuant increase of D.Generation, there are certain barriers
that have to be examined very carefully in order to succeed further
development of DG in the future.
There
are some barriers that
are
not technical and have to do with:
-the
regulatory
framework(for example deep charges should not be paid solely
by new distributed generators as they are not the only
party responsible for theconnection
reinforcements ,but the changes should divided amongst all contributing
generators)
-grid
connection issues
-planning
permission
andthe technical barriershave to do with
-forecasting
and scheduling of Demand and supplyin connection with location and time of the year
-and
also various problems that have to do with controlling and measuring
D.G