Back to home page



Distributed Generation (embedded Generation)

(regulatory framework /legislation/consultation papers.)


     Embedded Generation Working Group(EGWG)… the first step


Embedded generation is not a new concept. It has been a feature of the electricityindustry
since it began more than a century ago. But recent Government initiatives ongeneration from
renewable sources and combined heat and power (CHP) stations havefocused attention on how
embedded generators are treated in the energy market. Forexample, the recent report of the
Royal Commission on Environmental Pollution calledon the Government to review how electricity
networks can best be financed, managed andregulated in order to stimulate and accommodate large
contributions to energy suppliesfrom CHP plants and renewable sources, while maintaining reliability
and quality ofsupplies.

During the year 2000, the Embedded Generation Working Group(EGWG) had considered a wide

range of issues relating to embedded generation and published some  initial

recommendations for action by relevant bodies to help ensure that embedded generation

is treated on an equitable basis compared to other users of distribution and transmission

networks. (153 Kb)(click for the complete report)


The Group has identified that current arrangements are not conducive to the development

of embedded generation. This report puts forward a series of initial recommendations,

together with a proposed timetable to implement changes. Taking account of the physical

limitations of the networks themselves, and how they are planned and operated, the

recommendations focus on changes that would facilitate the connection of embedded

generation. There are also recommendations on regulatory, transparency and charging

issues as well as the wider questions of appropriate incentives and how network operators

will achieve their new Utilities Act duty to facilitate competition. However, it may be

that the removal of barriers by itself may not encourage the scale of embedded generation

implicit in the Government’s targets for renewables and CHP.

The Group’s role and its approach to its objectives have been unique. Its membership

comes from a wide range of stakeholders including Government (DTI, DETR and other

agencies), the regulator, Ofgem, and the industry. The Scottish Executive attended the

meetings as an observer. Industry members include representatives of different types and

sizes of generators; transmission and distribution companies; suppliers; and large and

small customers. The Group agreed at the outset to make its work as clear and readily

available as possible. Notes of its meetings and reports have been published on the DTI

website to enable all interested parties to see and contribute to the Group’s thinking.

One of the most striking features of the Group has been the open, frank and constructive

approach of all its members. Despite their different institutional and commercial

backgrounds and drivers, each of them has contributed in a positive way. Many mutual

misunderstandings amongst stakeholders have been dispelled. And most importantly,

members have found it possible to reach consensus views on most of the issues under

consideration.


Many of the Group’s initial recommendations concern the legislative and regulatory

framework for embedded generators and network operators. It will be for the bodies with

relevant responsibilities and powers to consider and implement change where

appropriate. The Group will have met its objectives when this happens. Its final report

and recommendations will be a catalyst for action and a means of tracking progress

against the challenging objectives it will set.


The Issues


 If Government’s targets for higher levels of CHP and renewable plant by 2010 are to

be achieved, distribution networks will have to be capable of accommodating far more

generators connected directly to their networks than we have now. (These are known as

‘embedded’ generators). Additionally, under the Utilities Act 2000, there is a new duty

on distribution businesses to facilitate competition in generation and supply. Present

regulatory framework, financial incentives and network design approaches are not

conducive to all of the above.

Much of the distribution network was developed pre privatisation to meet the growing

network demand. More recently, network development has been strongly influenced by

the incentives and risk exposures that the Distribution Network Operator's (DNO) current

regulatory environment provides. As a result of both of these factors, there are several

technical and practical limitations to expanding levels of embedded generation:

· network capacity restrictions in rural areas which limit connection of generators,

including renewables such as wind,

· Fault levels restrictions in urban areas which limit connection of generators such as CHP,

· Design standards which prevent the variable nature of loads, generation and network

capability being fully recognised.

  

There are also charging and transparency issues:

· Embedded generators are charged for the full reinforcement costs which result from

their connection. While these ‘deep’ connection charges provide a strong locational

signal, they also represent a financial barrier to new plants. If a major reinforcement is

triggered, there is no mechanism for sharing the costs of the reinforcement with

subsequent connectees. Other charging approaches may retain sufficient locational

signals, but provide more flexibility for sharing the cost of reinforcements between

those parties who benefit from them,

· DNOs have no further revenue stream from embedded plant because such plant pays

no distribution ‘Use of System’ (DUoS) charges. Other incentives on DNOs to

connect embedded plant are weak,

· Lack of published information about the best locations for embedded generation

means that potential generators have difficulty in determining charges and the best (or

worst) places to connect to the network.

Without significant changes to many or all of the above, the development of renewables
and CHP plant envisaged in the Government’s environmental targets could be

restricted. The full potential for embedded generation will only be realised if incentives

for all the key stakeholders are aligned to create the right commercial environment which

will enable embedded generation to contribute to a stable and secure network whilst

ensuring a diversity of fuel supplies in a more environmentally sustainable manner.


Recommendations

The joint Government/Industry Working Group on Embedded Generation Network

Access Issues (the Group) has identified a wide range of design, operational, charging

and disclosure issues where changes may be appropriate. In some areas, short-term action

is a real possibility. Many others require changes to the regulatory regime, design and

operational codes and procedures, and some aspects of the law. Many recommendations

will require significant changes in approach from DNOs, Ofgem and embedded

generators themselves.

The Group has two key recommendations.

Recommendation 1

 Ofgem should review the structure of regulatory incentives on

DNOs in the light of the new statutory duty on DNOs to facilitate competition, - in

particular to assess the effect this new framework will have on all the stakeholders

including DNOs, Generators, Customers and Suppliers.

It is likely that such a fundamental review would only be practicable at the next price

control review. Some changes are possible within the framework of the present price

control structure. Given the above, a co-ordinated and managed programme of work

needs to start now under OFGEM leadership to:

· Establish a charging regime for embedded generators that reflects the DNOs

duty to facilitate competition in generation as well as in supply. Ofgem, DNOs

and embedded generators should all discuss the scope for addressing the financial

implications of adopting a shallower form of charging principle for generator

connections in advance of the next price control review. This work should be

carried out in the context of a wider review of all entry and exit charges for

distribution networks.

· Review and prepare guidance that will allow DNOs to interpret design and

operational codes in such a way as to allow the contribution of embedded

generation to network performance to be taken fully into account. A review of

the codes themselves and of the governance arrangements for distribution

networks should follow.

· Establish more transparent and consistent arrangements for the provision of

information by DNOs to developers of embedded generation and demand and in

particular ensuring that the requirements of a proposed distribution licence

condition for a Long Term Development Statement are implemented to achieve

this goal.

Recommendation 2

A Group should be established under Government leadership to

co-ordinate and take forward the implementation of the present Group’s

recommendations for the longer term.

Work needs to start now if changes to the way DNOs design and operate their networks

are to be achieved in the longer term. This will need to complement the considerable

other work which has begun elsewhere (summarised in Appendix A).

 Without the changes recommended in this report, it is unlikely that the level of

embedded generation envisaged by the Government will be accommodated on

distribution networks. In reviewing these matters, solutions should be sought which are

equitable to all players, which do not impose excessive costs on customers and which

preserve security of supplies.


The rolle of OFGEM  (Office of Gas and Electricity Markets )

Ofgem is the Office of the Gas and Electricity Markets, regulating the gas and electricity
industries in Great Britain. Ofgem's aim is to bring choice and value to all gas and electricity
customers by promoting competition and regulating monopolies.Ofgem is governed by an
authority and its powers are provided for under the Gas Act 1986, the Electricity Act 1989 and the Utilities Act 2000.

The obstacles facing distributed generation

·        Today’s distribution networks have been built to deliver power from the national

transmission network to the end customer. Distributed generation, however,

requires more active distribution networks which allow electricity to flow in two

directions – to the electricity user for consumption in homes or businesses, and

on to the network when the user is exporting excess generation capacity.

·        Under the current arrangements, smaller renewable generators have found it

difficult and expensive to connect to the distribution networks.


Ofgem’s role in helping remove these obstacles

Ofgem is addressing the issues facing distributed generation to ensure that its

development is not unfairly treated by the way in which networks are currently

operated and regulated.

Following a consultation in September 2001, Ofgem is now proposing some

initial measures to embrace technological developments and provide a fair and

transparent regime for distributed generation, so it can establish itself in the UK’s

electricity market. Ofgem has also identified further changes that should be

actively considered over the coming months.

In looking at these issues, Ofgem’s overriding aim is to ensure that any future

changes continue to deliver to electricity customers a safe and secure,

good quality electricity supply at a fair price.

Ofgem’s proposals


These proposals are aimed at helping remove obstacles which might unfairly prevent development of distributed

generation by looking at

a)     what should be done to change the regulatory regime in the short term


allowing generators the option of spreading the cost of connecting to the distribution network

making it easier for domestic Combined Heat and Power generators (customers who have heating systems which

can generate electricity) to connect to the networks by establishing a standard connections procedure

reimbursing distributed generators some of the initial connection fee when another generator connects to the

same part of the network, which they have already paid for.

Network issues

clear information from distributors on preparation of quotations for connections to the network

clarify the technical and commercial benefits of distributed generation.

Metering

look at the best way to record and meter the amount of electricity that is used against the amount that is put back

onto the distribution network by a home with domestic CHP – and consequently how their bills should be

calculated to reflect it. This will make it easier for people to have domestic CHP in their homes.


b) what should be considered in the next distribution price control review, which is due to start this year.


developing appropriate incentives in the price control for distributors to connect distributed generation to

their systems

setting out more clearly the difference between the amount that generators are charged for connecting to the

system and the amount they pay to put electricity on to the network more clearly

how distributed generation should be taken account of within the distribution price control process.


A brief history …….

 

 


Back to home page