Back to home page


 

Economics


Project costs can be broken down into three categories: 1) capital  2) operation & maintenance  3) disposal.


The economic analysis for selecting the least-cost installed capacity for the hydro plant was based upon the

standard industry rule-of-thumb that capital cost of generation equipment and installation is £1000 per kW of

installed capacity (in the range 100kW to 1000kW).  The connection cost was estimated at £208000. 

Generation operation and maintenance costs were set at 2% of generation capital cost per annum, and

transmission operation and maintenance at 6% of connection capital cost per annum.  These values are

estimates.In the light of further information on costs, a spreadsheet has been provided here for modifying

the analysis.


Considering that the investment is spread across the life of the plant (i.e 40 years) with a discount rate of 8%,

it was concluded that the optimum economic level of generation is 400kW installed capacity for the small scale

hydro plant.Graph 3 shows the results of the economic comparison between wind turbines and small scale hydro

plants for various installed capacity.


 

 

 

 

 

 

 

 

 

 

 

 

 



Graph 3.Economic comparison between wind turbines and small scale hydro

 


The power output, as supplied to the local demand, is shown in graph 4.

 



graph 4.Power output, as supplied to the local demand.


From the above graph it can be seen that the daily base load is met by the hydro plant
The output of the plant is not constant,however,as the water resource can not maintain a constant energy
supply to the turbine (in times of very low water levels). These variations can be seen on the graph, where there
are dips in the supply line. Nevertheless a high level of generation is maintained, which gives rise to a high
capacity factor - in this case greater than 90%. This is the result of utilising only a relatively small proportion of the
maximum possible potential, in order to meet the requirements of local demand. More energy could be extracted from
the resource, but the supply profile would be far more unpredictable due to the greater degree of fluctuations.
But as this is the economic optimum generation level, to tap the resource any further would be uneconomical
because the turbine would be rated even
farther into the intermittent load zone, i.e. much of the time the generation
capability would be greater than the demand.
By means of utilising only a small proportion of such a large resource the
energy cost for small-scale distributed generation can be brought into competitiveness with traditional forms of generation.
In this the cost of electricity was calculated at 4.9p per kWh - if spread across the life of the plant.
 


Investors


Energy costs can vary depending on the return required by the investor.Typically, public

sector investments demand a rate of return of only about 8% (excluding inflation), and require

payback over the life of the plant (40yrs.).A private investor will require a greater rate of

return - perhaps 15% - and a shorter payback period - often 15 years. 

The effect on the cost of energy production is illustrated,with this example, in the graph below.

 

 

 

 

 


Back to home page