Financial Analysis

Introduction - Why LCOE?

To enable investors, energy developers and governments to compare vastly differing technologies on a comparative scale, the cost analysis instrument known as Levelised Cost of Electricity generation is widely used in industry [1]. This tool, known in short as LCOE, is a summation of the lifetime costs associated with developing, operating and decommissioning an energy generation plant divided by the lifetime energy production.

There has been some criticism of the LCOE approach as it does not account for the variable output of renewable technologies [2]. However, in the UK there remains a strong case for using LCOE, as the recent implementation of the Energy Market Reform [3] effectively means long term energy sales prices are fixed for the first 15 years at an agreed Strike Price. This allows a simple comparison to be made between the LCOE and the strike price – if the Strike Price is higher than the LCOE, the project is effectively profitable.

LCOE must, however, be used with caution when wind and wave are combined – the guideline Strike Price for offshore wind is £155/MWh whereas for wave energy it is £305. As such, the proportion of revenue generated by each method must be effectively “sold” at its relevant strike price.

Methodology

To allow the LCOE to be calculated for a wind farms of variable size, the Capital Investment (CAPEX), operating costs (OPEX) and decommissioning costs (DECEX) were all calculated per unit of installed rated capacity (£/MW). This allowed the cost calculation to be used with variable inputs to allow various scenario and sensitivity analyses to be carried out.

more about Methodology

The project was assumed to be operational over a 20 year period. CAPEX investments were assumed to occur 4 years prior to the start of the 20 year operating period, with the installation portion being allocated at 1 year prior to the operating period. DECEX was assumed to occur in year 20 – therefore, the entire project duration is 24 years. Discounting was used and the rate was set at 3.5%, as recommended by the UK Treasury to reflect the intergenerational benefits of renewable energy projects such as this one. For all cost inputs, no allowances have been made for future cost reductions and inflation was not included.

Where:

LCOE = the average lifetime levelised cost of electricity generation

Cxt = Capital Expenditure in the year t

Oxt = Operating Expenditure in the year t

Et = Electricity Generation in year t

r = Discount Rate

n = Economic life of the system

Click here to download the financial model

Platform Capex

The construction of the platform was based on the Float Incorporated Offshore Ocean Energy System. As such, we were provided with a cost calculator which, based on our specific design parameters, estimated the material and construction cost of the basic platform structure. In addition to this, costs were either found from reference material, or assumed based on similar designs for the facilities and components specified for the design.

more about Platform CAPEX
  • Mooring Cost
  • Accommodations
  • Workshop
  • Crane
  • Heli Deck
  • Boat Landing Area
  • Backup Electrics
  • Platform Component CAPEX (£m) References/Notes Notes
    PSP Concrete Hull 238.4 Float Incorporated Cost Estimation Calculator
    Mooring Cost 23.8 [4] Estimated at 10% of Hull Cost
    Accommodation 20.0 [5]
    WEC Cost 46.0 Float Incorporated Cost Estimation Calculator
    Workshop 10.0 Assumption Assumed to be 50% of Accommodation Cost
    Crane 1.4 [6] 2nd Hand Liebherr LR 1300 Crawler
    Heli Deck 0.7 [4]
    Boat Landing Area 1.5 [4]
    Backup Electrics 1.0 [4]

    Platform OPEX

    In addition to the capital cost of the constructing the platform and its facilities, an important input for the cost assessment was the annual operating cost of the platform. This includes general maintenance and upkeep, insurance costs & staffing costs. As the platform is designed to be self-powering, only backup electricity supply is required – as such no fuel costs have been included for the platform itself.

    more about Platform OPEX
    Platform Component Rate (%) Annual Operating Cost (£)
    PSP Concrete Hull 1 2,384,440
    Mooring Cost 1 238,444
    Accommodation 3 600,000
    WEC Cost 3 1,380,388
    Workshop 1 100,000
    Crane 1 14,092
    Heli Deck 1 7,046
    Boat Landing Area 2 30,000
    Backup Electrics 1 10,000
    Total Platform Maintenance 4,764,410
    Personnel Category Salary (£) Number Required Annual Cost (£)
    Offshore Installation Manager 100,000 2 200,000
    Medic/Coordinator 50,000 2 100,000
    Stewards 35,000 6 210,000
    Crane Operator 35,000 2 70,000
    Cooks 35,000 6 210,000
    Maintenance Technician/Electrician 50,000 4 200,000
    Total Annual Staff Cost £990,000
    Reference: [7] converted from $US and rounded to nearest £5k

    In addition, insurance was included at a rate of 2% of the total OPEX. [8]

    The annual operating expenditure was therefore calculated as £12.6m for the base case.

    Wind Turbine CAPEX

    Offshore wind turbine costs are covered well in literature, government publications and industry summaries. As such, the process is well defined. Floating offshore wind farms are a novel concept and have not yet been proven in large arrays.

    more about Wind Turbine CAPEX

    One study into the predicted costs of floating offshore wind farms was carried out by Myhr [9]. This paper used a bottom-up approach to assess the lifecycle costs of developing and operating a floating offshore wind farm. It also used fixed, bottom mounted offshore wind turbines as both a comparison case, and to validate the cost model.

    In our analysis, it was necessary to calculate the CAPEX for 3 different scenarios:

  • 1. Standard Floating Wind Turbine (using Statoil Hywind base, which has been identified as the market leader)
  • 2. Floating WT based on our Installation & O&M strategy using TETHYS (most inputs same except substation/installation/OPEX)
  • 3. Platform Mounted Wind Turbine
  • In all cases 6MW Siemens turbines were used.

    To validate our model, the project inputs (depth, distance etc.) were set to be the same as given in the Myhr paper. The base case CAPEX of £2.72m/MW (3.52m €/MW) for a standard Offshore Floating Turbine was within 8% of the cost predicted by Myhr.

    1. Standard Floating Wind Turbine

    Catergory Subcategory Reference Cost Site Depth/Distance Reference Size (MW) £/MW Reference / Notes
    Development and Consenting 104,106,000   500 161,142 [9]
    Production and Acquisition Tower & Turbine 7,475,000   5 1,157,034 [9]
      Floating Substructure 3,740,000   5 578,904 [9]
      Mooring 401,250 100 5 62,108 See Mooring Costs
      Export Cable 443,000 75 500 51,428 [9]
      Substation 161,700,000   500 250,290 [9]
      Substation Base Cost 23,800,000   500 36,839 [9]
      Inter Array Cable 281,000 161.50 500 70,244 Needs to be Calculated per Turbine
    Installation and Commissioning Construction Phase Insurance 50,000   1 38,696 [9]
      Exp Installation 590,000 75 500 68,493 [9]
      Inter Array Installation 190,000 161.50 500 47,496 Needs to be Calculated per Turbine
      WT Installation 786,000   5 121,662 [9]
      Mooring Installation 500,000   5 77,393 [9]
    Total Capex      2,721,735 per MW

    2. TETHYS Floating Wind Turbine

    The standard offshore wind turbine was used as the basis for wind turbines installed using the TETHYS concept; however, the Substation & Export Cable were calculated per MW for the entire system incorporating the wave energy output. In addition, no Substation Base was required. Finally, wind turbine installation was assumed to be 0.5 x Myhr as the installation method differed significantly. The CAPEX was calculated to be £2.27m/MW.

    CategorySubcategoryReference Cost (£)Site Depth/DistanceReference Size (MW)£/MWReference / Notes
    Development and Consenting 104,106,000  500 161,143 [9]
    Production and AcquisitionTower & Turbine 7,475,000  5 1,157,034 [9]
     Floating Substructure 3,740,000  5 578,904 [9]
     Mooring 401,250 1005 £62,108 See Mooring Costs
     Export Cable    Calculated for total "system"
     Substation    Calculated for total "system"
     Substation Base Cost 500 No SS Base Required
     Inter Array Cable 281,000 85500 36,971 Needs to be Calculated per Turbine
    Installation and CommissioningConstruction Phase Insurance 50,000  1 38,697 [9]
     Export Cable Installation 590,000 75500 68,493 [9]
     Inter Array Installation 190,000 85500 24,998 Needs to be Calculated per Turbine
     WT Installation 786,000  5 60,831 [9]
     Mooring Installation 500,000  5 77,394 [9]
    Total Capex     2,266,574 per MW

    3. Platform Mounted Wind Turbine

    Finally, the CAPEX was calculated for the two platform-mounted wind turbines. These were found to be significantly less expensive due to not requiring moorings, floating bases and inter-array cables. The CAPEX was calculated to be £1.34/MW.

    Capex Comparison

    It should be noted that the above CAPEX values are not directly comparable as only the standard floating OWT contains costs for the substation and export cable. The chart below shows the CAPEX with these costs removed.

    As can be seen, the installation method and removal of the substation base reduces the CAPEX; however, not nearly as significantly as siting the turbine on the TETHYS platform itself.

    Wind Turbine OPEX

    In order to compare our proposed concept to the current industry leading concept of using a mothership it was necessary to use both a bottom-up approach and cost estimates from literature. One of the main aims of our concept was to reduce the wind farm operation and maintenance costs by minimising the time taken, and distances travelled by crew transfer vessels taking technicians from the base to the wind turbines to carry out maintenance, in addition to minimising the use of expensive offshore lifting vessels, which can cost upwards of £200,000 per day.

    more about Wind Turbine OPEX

    First, the operating costs of operating crew transfer vessels from the platform/mothership to the wind turbines were calculated using a bottom-up approach to calculate charter rates, fuel use and staffing costs based on the estimated number of visits and distance to each turbine.

    The crew transfer vessel specification is:

    DescriptionCost (£)/QuantityUnit
    CTV Fuel Use Rate446litres Per Hour
    CTV Fuel Cost0.83per litre
    CTV Charter Rate3,000per day
    CTV Skipper 60,000per year
    CTV Speed15knots

    The number of wind turbine visits was assumed to be 10 per year. A more thorough analysis could be carried out using Monte-Carlo simulation [5]; however, for the purposes of this investigation this simplification was considered acceptable. Each CTV could service 30 turbines per year and required two skippers on back-to-back rotation. In addition, the number and cost of crew (O&M Technicians, O&M Managers etc.) was calculated based on the following rates

    DescriptionNumber of TechniciansCost (£)Number Required per Turbine*
    Offshore O&M Technicians60 51,8540.6
    Offshore O&M Managers2 91,3240.02
    Offshore O&M Administrative6 46,4360.06
    Onshore O&M Assistants3 38,6970.03

    *After calculating the number of personnel required for each wind farm size, the number was rounded to the nearest integer.

    The annual cost was calculated over a range of different sized wind farms, from 7 to 250 turbines. The relationship was found to be relatively linear, and therefore a trend-line was overlaid in excel and its equation noted. This equation was then used in the overall cost model to calculate the cost of this portion of the O&M.

    Second, using the CAPEX cost references in the Myhr paper as a starting point, which consisted of wind turbine spare parts, CTV & personnel, and the cost of operating the mothership, the cost of each proportion was calculated. To achieve this it was necessary to begin by separating the wind turbines spares, this was done by finding the cost associated with solely the CTV, personnel and mothership from a paper by Dalgic [5]. Then, because the cost for the CTV & Personnel had already been calculated using a bottom-up approach, the resultant cost of the mothership (excluding the CTV & personnel) was found. Finally the proportion of the CAPEX cost relating to WT Spares was back-calculated and found to be 1.39% of CAPEX. Again, a validation check was carried out by using the same project related parameters as the reference papers and the result was within 4% of the predicted cost.

    The total OPEX for the standard floating offshore wind turbine was calculated to be £97k/MW, while the TEHYS version was £69k/MW. Due to not requiring CTVs, the two platform mounted wind turbines OPEX is significantly reduced at £47k/MW.

    Export Cable CAPEX

    As discussed in the design section a DC substation has been assumed. A 500 MW unit costs £143m [9], therefore a CAPEX of £286,000/MW has been assumed. The export cable costs are not available as the technology is not mature. As such, an escalation factor of 100% has been assumed for the export cable cost. The export cable CAPEX is therefore £1,772 per MW per km.

    Export Cable OPEX

    Due to the complexity of the calculation required to assess the OPEX costs for the substation and Export Cable, coupled with its low impact on the overall cost, a value of 1% of CAPEX was assumed for the operating and repair costs of these components. For the case of the mothership these costs are included in the WT OPEX.

    Project Specific Inputs & Overall Assumptions


    Project Inputs Table
    DescriptionQuantity/PercentageUnitNotes/References
    Project Lifespan20Years 
    Discount Rate For Money3.5% [10]
    $/£ Exch Rate0.705 XE.Com 09/03/2016
    €/£ Exch Rate0.774 XE.Com 09/03/2016
    Strike Price WTs£155per MWhCfD
    Strike Price WEC£305per MWhCfD
    Export Cable Length75kmTo Centre of Site Area
    WT Rated Power6MW 
    Site Water Depth 100mAverage of Site Area
    WT Availability93% [9]
    Electrical Array Losses2% [9]
    Aerodynamic Array Losses7% [9]
    Other Losses3% [9]
    WEC Availability90% Float Incorporated Estimate
    WT Spares Cost1.39% Calculated

    Assumption: cost of energy stays at strike price after 15 years.

    Matched Wind & Wave

    One of the objectives of this project was to create a platform that harnessed the power of both wind and wave. As discussed, the optimum ratio of wind to wave for the West Coast of Ireland [11] was found to be 20% Wave and 80% wind. It should be noted that these ratios correspond to the annual average electricity generation, not to rated power, as the technologies have different output characteristics.

    more about Matched Wind & Wave

    The LCOE model was used to calculate the cost of electricity production for two scenarios:

  • Industry Standard WEC Capacity Coefficient – 15%

  • Float Incorporated Estimate of WEC Performance – 41%

  • In both cases the wave energy was calculated using the following equation:

    Annual Energy Yield=Capacity Coefficient x Rated Power x 8760 (MWh)

    This was calculated for both the low and high cases, and then re-calculated using the WEC availability factor of 90% - the resulting annual energy yields were:

    CaseAnnual Energy Yield (MWh)After Availability Losses (MWh)
    Low (15% Capacity Coefficient)3784334059
    High (41% Capacity Coefficient)10343893094

    To maintain the 20% wind to wave ratio, the number of wind turbines in the floating wind farm had to be matched in each case. As a result, the number of wind turbines required in the low case was 6 and in the high case 18. In both cases, 2 wind turbines were situated on the platform and the remainder would constitute the floating array surrounding the platform.

    The wind farm annual energy yield was calculated using the methodology described.

    Results

    The levelised cost of energy was calculated and as can be observed in the previous chart – the low case LCOE is £296/MWh and the high case £144/MWh. In both cases, due to the relatively low number of wind turbines in the array, the platform CAPEX and OPEX constitute a large proportion of the overall LCOE.

    more about Results

    To evaluate the profitability of the two cases, the energy sales price were set at the average contracts for Difference Strike Prices as follows:

  • Wind - £155/MWh

  • Wave - £305/MWh

  • As a result, the low case would make a loss of 60% and the high case would make a profit of 22% over the lifetime of the project.

    Discussion of Results

    It is clear from observation of the results that if the capacity coefficient of the wave energy device is lower than that predicted by the designers of the technology, Float Incorporated, then, in the configuration analysed, the TETHYS is not viable – this is due to the large capital investment and operational costs associated with the platform. If the technology is proven to be successful then the platform will result in a profit while maintaining the ratio of 20% wave energy to 80% wind energy.

    TETHYS vs Mothership

    The two main objectives of this comparison were to:

    1. Compare the TETHYS concept with the industry leading technology

    2. Analyse the effect of increasing the size of the surrounding wind farm on the LCOE & Profit

    more about TETHYS vs Mothership

    The same inputs were used, with the main variable being the number of wind turbines and therefore the annual energy yield. As the number of wind turbines increases, conversely the wind to wave ratio cannot be maintained at 20%. The results were analysed from 25 to 150 wind turbines, representing wind farm sizes consistent with those currently in operation or in planning.

    As can be observed in the previous chart, as the wind farm size increases the LCOE reduces in all three cases. It is interesting to note the LCOE for the mothership tends to level off beyond 100 turbines, while the TETHYS high and low cases continue to reduce more significantly as the wind farm size increase – due to the CAPEX of the platform becoming a smaller proportion of the overall cost. It is also evident that the LCOE is not significantly different in all three scenarios except for the smallest size. Small changes to any of the assumptions could easily change which scenario is the least expensive – however, the key point is that the LOCE is comparable.

    While LCOE is a good measure to compare different technologies, as was previously discussed; however, due to the different strike prices attracted by wind and wave, it is worthwhile comparing the expected profits in the three scenarios and the results are presented below:

    Again, with increasing wind farm size the profits show marked improvement and in all cases. A 150 turbine TETHYS concept with the higher performance (41% capacity coefficient) wave energy collector would outperform the mothership with an expected annual profit of 54%, compared to 47% for the mothership.

    Sensitivity Analysis & Discussion

    Both the TETHYS concept and the Mothership concept use the same type of floating wind turbine, therefore no sensitivity analyses were carried out with regard to the component costs of the wind turbines. As previously mentioned, while there is significant scope for changes material costs (both upwards and downwards) and also cost reduction through technology improvement – for the purposes of this study they are assumed to be constant.

    more about Sensitivity Analysis & Discussion

    The main areas where either assumptions were made, or there was significant uncertainty that could result in changes to the LCOE were:

  • Substation and Flexible Export Cable Costs

  • Mothership Charter Rate & Fuel Cost

  • PSP “width” (front to back dimension)

  • Concrete Cost

  • Discount Rate used in NPV Calculation

  • Wind Turbine Installation using TETHYS as an Installation Base

  • Wind Turbine Energy Yield

  • Wave Energy Climate

  • Therefore, sensitivity analyses were carried out for these variables using the 50 wind turbine reference case for either the TETHYS “high” scenario (with 41% Wave Energy Capacity Coefficient).

    Discussion

    Substation and Flexible Export Cable Costs

    As described the best option for the electricity export system is DC converters/substation and a flexible DC export cable (due to the movement of the platform). DC substations are not uncommon; however, the flexible cable has only recently come on the market and, as such, the costs are unobtainable. For this base case analysis, the export cable was assumed to be twice the cost of a regular DC cable, low and high cases were assumed to be 1 x DC Cable cost and 4 x DC cable cost respectively. The export cable is often cited as one of the main cost contributors for offshore wind. In this analysis it is clear that the cable cost will impact the overall cost, but it is not a single over-riding factor.

    Mothership Operating Costs

    The mothership concept uses a substantial quantity of fuel for station holding and operations – typically around 25000 tonnes per year resulting in a cost of about £10m per year (depending on the scenario). Fuel prices are known to fluctuate and reports indicate that by 2030 prices are likely to increase by 1.5x the current price [12]. Additionally, charter rates are set by the market and also fluctuate. For the purpose of the sensitivity analysis fuel costs were set to £550/ton for the base case, £440/ton (0.8x) for the low case and £825/ton (1.5x) for the high case. The mothership charter rates were set to £30k for the low case, £40k for the base case and £50k for the high case.

    It is clear that these costs have a similar effect on the LCOE as the export cable cost and, unlike capital expenditures the cost cannot be agreed during the pre-construction stage – throughout the lifetime of the project the financial performance will be influenced by these variable costs.

    TETHYS Size

    The breadth dimension of the platform is fixed, dependant on the required rated power of the wave energy converters, conversely the front to back “width” of the platform can be minimised as far as possible to reduce costs. The only constraints are the structural integrity, stability and topsides facilities requirements. The base case dimensions was 50m, and the low case was set to 40m; the high case to 60m. While it clearly does affect the LCOE, it is not as critical as some of the other variables.

    TETHYS Concrete Cost

    Since the platform uses over 300,000 tons of pre-stressed concrete, the cost of this could become an important factor. Historical cost data was assessed to find the range of costs in the last 10 years [13]. The low case was set to 92% of the base case and the high case set to 106% of the base case. Again, the overall costs is influenced by this variable and, while the historical data show the variance is not large – in future the costs could change more significantly.

    Discount Rate

    The discount rate is used to discount future cash flows to the Present Value. Selecting the correct rate is a topic which has been researched, discussed and guidelines have been published. There remains, however, considerable disagreement as to which rate to choose. It is common practice to use a rate of 10% [14], due to the risks and unknowns associated with first of a kind renewable energy projects. However, using high rates heavily penalises projects with high initial investments and low decommissioning costs, conversely, it is beneficial to use high discount rates for projects with very high decommissioning costs, such as oil & gas production and nuclear power [15]. It has been argued that projects that provide substantial social and environmental benefits to future generations should be assigned a lower discount rate [10]. In addition, the TETHYS platform useful life is predicted to be over 50 years and, as such, it can continue to provide wind farm support facilities to a second wave of wind farms in the future.

    As such, the discount rate was varied from 3% to 4%, with a base case of 3.5% which is the rate recommended by the UK Treasury for renewable projects [10].

    Inspection of the above chart shows that even a 0.5% change in discount rate can substantially influence the LCOE. And, due to the higher capital but lower operating costs of the TETHYS platform, the discount rate results in a bigger fluctuation than with the Mothership.

    As “super high” case was set at 10% to evaluate how this affected the economics – in this case the LCOE increased to £163/MWh for the TETHYS “High” Case and £146/MWh for the Mothership. Clearly selection of discount rates is contentious and highly influential.

    Wind Turbine Installation

    Late in the development of this project, it became clear that the TETHYS Concept could potentially reduce installation costs. However, with the available time it was not possible to assess the actual costs of the installation process. The base case was assumed to be 50% of the installation costs predicted by Myhr [9] as it was assumed that no inshore installation base would be required, with the associated heavy lift cranes etc. In addition, the need for upright towing of the assembled turbines would be lower, therefore significant savings would be made in tug charter and fuel costs. As these were based on assumption, the installation cost was assumed to be 25% of the Myhr estimate for the low case and 100% for the high case.

    Again, considering the ever present drive for reducing LCOE – minimising of the installation cost of the wind turbine is worthwhile, but it is not one of the main cost drivers.

    Wind Output

    Somewhat surprisingly, a small increase or decrease in the output of the wind turbines can have a substantial effect on the overall cost. For both the TETHYS “High” case and the Mothership the base case power coefficient was set to be 50% and high case to 56%. When taking into account availability, electrical and aerodynamic losses this results in a base case of 44% Load Factor (low case 41.5% and high case 46.5%). As can be observed this has a noticeable impact on the LCOE but there is no real difference in the variance between the Mothership and TETHYS cases.

    Wave Energy Climate

    For the location selected for our project, like most UK sites, there is no high resolution wave data, only low resolution ranges. Therefore, this variable was assessed for its impact. The wave energy output for the TETHYS “High” scenario was 93090 MWh/yr in the base case. The high and low cases were set to 0.8x and 1.2x the base case.

    Total Cost of TETHYS Concept

    The final stage of the financial analysis was to calculate the total cost of the TETHYS platform, using the previously discussed ratio of 20% wave energy extraction and 80% wind energy. For this analysis the wave energy collectors were assumed to have a 41% capacity coefficient as per Float’s predictions. To balance this 16 wind turbines were required, with 2 on the platform and 14 in the surrounding wind farm.

    The capital cost of the wind turbines and the platform make up 68% of the LCOE:

  • Platform Total Capital Cost - £342m (inc £1.5m installation)
  • Wind Turbine Total Capital Cost - £226m (inc. £25m installation)
  • The operations and maintenance costs make up the majority of the remainder of the LCOE (30%) is attributed to operations and maintenance (O&M):
  • Platform O&M - £12.6m/yr
  • Wind Turbine O&M - £16.2m/yr
  • The final 2% is assigned to decommissioning; it should be noted that the use of discounting to calculate net present value results in the decommissioning costs appearing to be much lower than would be expected.

    The final total summation of costs over the 20 year lifetime of the project, discounted to net present value is £851m, while the total sales from wave are £364m and wind £730m, which combined are £1,094m, therefore resulting in a profit before tax of 22%.

    Financial Analysis Summary

    It has been shown that the TETHYS platform can harness the power of wind & wave and not only return a respectable profit, but also compete with the industry benchmark the mothership.

    more about Financial Analysis Summary

    However, it would be naïve to think that this is the end of the story – the analysis presented was limited in scope and resource and therefore a number of assumptions and simplifications were required. Sensitivity analysis was carried out on the main assumptions and uncertainties to test the cost model’s susceptibility to changes in these inputs. Discount rate and the wind energy yield proved to be the most influential; however their effect is not vastly dissimilar between the mothership and TETHYS, meaning that these assumptions doesn’t significantly affect the comparison between the two.

    A final note is that the analysis was carried out over a period of 20 years, due to the limit in useful life of wind turbines. It is estimated that the platform’s useful life could exceed 50 years, making the lifecycle cost more competitive.

    Go to Conclusions

    References
  • [1] IRENA, “Renewable Energy Technolgies Cost Analysis Series,” Bonn, Germany, 2012.

  • [2] F. Ueckerdt, L. Hirth, G. Luderer, and O. Edenhofer, “System LCOE: What are the costs of variable renewables?,” Energy, vol. 63, pp. 61–75, 2013.

  • [3] DECC, “Investing in renewable technologies – CfD contract terms and strike prices,” no. December, p. 12, 2013.

  • [4] G. Petrie, “Semi-Submersible Feasibility Study,” 2013. [Online]. Available: http://www.seasteading.org/semi-submersible-seastead-community-feasibility/.

  • [5] Y. Dalgic, I. Lazakis, I. Dinwoodie, D. Mcmillan, and M. Revie, Cost benefit analysis of mothership concept and investigation of optimum chartering strategy for offshore wind farms, vol. 80, no. 0. Elsevier B.V., 2015.

  • [6] Bigge, “LIEBHERR LR1300,” 2015. [Online]. Available: http://www.bigge.com/crane-sales/cranes/liebherr-lr1300/1780/. [Accessed: 25-Mar-2016].

  • [7] HAYS, “Global Salary Guide 2015,” Houston, TX, 2015.

  • [8] G. . Dalton, R. Alcorn, and A. . Lewis, “Operational expenditure costs for wave energy projects O&M , insurance and site rent,” Third Int. Conf. Ocean Energy, vol. 35, no. 2, pp. 443–455, 2010.

  • [9] A. Myhr, C. Bjerkseter, A. Ågotnes, and T. A. Nygaard, “Levelised cost of energy for offshore floating wind turbines in a life cycle perspective,” Renew. Energy, vol. 66, pp. 714–728, 2014.

  • [10] HM Treasury, “The Green Book : Appraisal and Evaluation in Central Government,” London, 2003.

  • [11] F. Fusco, G. Nolan, and J. V. Ringwood, “Variability reduction through optimal combination of wind/wave resources - An Irish case study,” Energy, vol. 35, no. 1, pp. 314–325, 2010.

  • [12] Lloyd’s Register, “Global Marine Fuel Trends 2030,” 2014.

  • [13] M.-A. I. Office, “Producer Price Index - Concrete and related products,” 2016. [Online]. Available: http://www.bls.gov/regions/mid-atlantic/data/producerpriceindexconcrete_us_table.htm.

  • [14] DECC, “DECC Electricity Generation Costs 2013 - Publications - GOV.UK,” no. July, 2013.

  • [15] T. S. LaGuardia and K. C. Murphy, “Financing and economics of nuclear facility decommissioning,” Nucl. Decommissioning Planning, Exec. Int. Exp., pp. 49–86, 2012.