Home Overview Background Project Conclusions Resources


 

 

 

 

 

 

 

 

 

 

Xscape Site - Case study

Back

Contents       

1. Introduction

2. Objectives

3. Simulation

    3.1 Office

    3.2 Canteen

    3.3 Drying Room

    3.4 Subcontractor’s Cabin

4. Results Summary

 

 

This case study is conducted in order to assess the current and proposed situation for one office, the canteen and the drying room of the contractor’s accommodation as well as one subcontractor’s cabin in the construction village at Laing O’Rourke’s Xscape site. The proposed situation is based on implementing previously identified energy efficiency measures in each of these areas. This case study is based on the actual room sizes occurring in the Xscape construction village and also takes into account the surrounding area of the various rooms as well as the working behaviour of all employees. Working hours are assumed to be 11 hours per day during 5 days a week and 52 weeks in a year.

 

 Back to Top

The objectives of this case study are to determine the following qualities for each area for our proposed situation in comparison to the current situation on the Xscape construction site: 

1.       Annual energy demand

2.       Annual energy costs

3.       Annual carbon emissions

4.       Thermal percentage dissatisfied on a typical winter day

5.       Thermal comfort on a typical winter day

Further outcomes from the case study will be:

 

1.       Investment costs

2.       Payback periods

 Back to Top

Detailed dynamic thermal modelling simulations have been conducted with the following models: 

  •          Office: 3m x 4m office room (improved insulation)

  •          Canteen: 9.5m x 3m cabin (improved insulation)

  •          Drying Room: 9.5m x 3m cabin (improved insulation)

  •          Subcontractor’s Cabin: 9.5m x 3m cabin

  •   Conventional cabin model (poor insulated)
  •   Improved cabin model (well insulated)

 

 

 

 

 

 

 

                       

 

 

                         Office Model                                        Cabin Model

 

For all simulation a climate file for Oban (1994) has been used. The heating season has been defined for 01 October to 31 March (26 weeks).

Back to Top

The office is a 3m x 4m room with 1m2 glazing area and has the following characteristics:

  • 2 occupants (7:00 – 18:00)
  • 1 computer + 1 printer (7:00 – 18:00)
  • North orientated
  • Infiltration: 3ac/h during work hours (doors mainly open)
  • 1 x 2kW heater and 2 x 36W lamps

Current situation: The following assumptions have been made.

Heating behaviour of occupants:

  • 7:00 – 8:00 heater on maximum power (1 x 2000W)

  • 8:00 – 18:00 heater on low power (1 x 750W)

Lighting behaviour of occupants:

  • 7:00 – 18:00 lights on

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

226.5 kWh

Heating

1235 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

40.53 % (16.51% standard variation)

Thermal comfort 1

1 h (mainly overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

 

Proposed Situation:  Following energy efficiency measures have been applied

  • High frequency ballasts
  • Day light control system
  • 1.5kW heater with automatic temperature control (starting time: 6:00)

 

The following assumptions have been made:

Heating:

  • Heating control to maintain a dry bulb temperature of 20°C

Lighting:

  • 25 % less lamp rating (HF control)

  • 65 % annual savings through day light control (hardly surrounding buildings; clean windows, little use of blinds)

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

59.5 kWh

Heating

471 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

8.25 % (10.05% standard variation)

Thermal comfort 1

10 h (mainly overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

 Back to Top

The canteen consists of 5 cabins and has the following characteristics:

  • Occupied by workers from 10:00 to 11:00 and 13:00 to 15:00
  • Occupied by cleaner from 11:00 to 12:00
  • 4 x 2kW heaters and 25 x 36W lights
  • Infiltration: 2ac/h during tea and lunch time, otherwise 1ac/h

 

Current situation: The following assumptions have been made.

·        

      Heating behaviour of occupants:

  • 7:00 – 9:00 heaters on maximum power (4 x 2000W)

  • 9:00 – 13:00 heaters on medium power (4 x 1250W)

Lighting behaviour of occupants:

  • 7:00 – 18:00 lights on

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

2831.4 kWh

Heating

4680 kWh

 

 

For a typical winter day (8:00 – 16:00)

Thermal percentage dissatisfied

52.63 % (19.77% standard variation)

Thermal comfort 1

0.5 h (mainly overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

The picture below demonstrates the dry resultant temperature inside the canteen on a typical winter day. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature.

 

 

 

 

 

 

 

 

 

 

 

 

 

                                               

 

 

 

                                                        Ambient and canteen’s dry resultant temperature

 

 

There is a discomfort inside the canteen due to overheating and poor air quality.

 

Proposed Situation: Following energy efficiency measures have been applied.

  • High frequency ballasts
  • Occupancy sensor for lights
  • 1.5kW heater with automatic temperature control (set from 8:00 to 15:00)
  • 5 ventilators with 550m3/hr with heat recovery and CO2 sensor (rated 150W)

The following assumptions have been made:

Heating:

  • Heating control to maintain a dry bulb temperature of 20°C

Lighting:

  • 25 % less lamp rating (HF control)

  • 64% annual energy savings (lights are on from 10:00 to 12:00 and 13:00 to 15:00)

Ventilation:

  • Switched on 4h per day

  • 7.7 ac/h per cabin with 70% heat recovery

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

764.5 kWh

Heating

3550 kWh

Ventilation

780 kWh

 

 

For a typical winter day (8:00 – 16:00)

Thermal percentage dissatisfied

13.78 % (17.95% standard variation)

Thermal comfort 1

4 h (mainly overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

As stated in the table, the dry resultant temperature cannot be maintained over the whole day. However, a comfort temperature of 20°C dry resultant temperature is maintained during tea and lunchtime as shown in the graph below. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
                                           Ambient and canteen’s dry resultant temperature 

 

 Back to Top

The drying room consists of 2 and a half cabins and has the following characteristics:

  •          Intermittent occupied (mainly at tea and lunchtime and before work end)

  •          2 x 2kW and 8 x 150W heaters

  •          9 x 36W lamps

  •          Infiltration: 1.5 ac/hr during working hours

Current situation: The following assumptions have been made

·           Heating behaviour of occupants:

  • 0:00 –24:00: 2kW heaters on medium power (2 x 1200W)
  • 0:00 –24:00: 150W heaters on full power (8 x 150W)

        

Lighting behaviour of occupants:

  • 7:00 – 18:00 lights on

 

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

1019.3 kWh

Heating

22464 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

88.37%  (24.3% standard variation)

Thermal comfort 1

0 h (always overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

The picture below demonstrates the dry resultant temperature and ambient temperature inside the drying room for a typical winter working day. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                         Ambient and cabin’s dry resultant temperature

 

It is shown that a dry resultant temperature about 40°C is maintained 24 hours during working days without ventilation. It is obvious that there is wastage of energy in addition to the problem that the clothes do not dry overnight.

 

Proposed Situation: Following energy efficiency measures have been applied.

·        

  • High frequency ballasts
  • Occupancy sensor for lights
  • 5 x 1.5 kW heater with automatic control to replace all existing heaters
  • 3 Ventilators with 220m3/hr with heat recovery and humidity sensor (rated 130W)

The following assumptions have been made:

·         Heating:

  • Heating control to maintain 20°C dry bulb temperature (24h per day)

·         Lighting:

  •  25 % less rating (HF ballast)
  •  Lights switched on for 20% of working hours

·         Ventilation:

  • Switched on 24h per working day
  • 3 AC/hr per cabin with 75% heat recovery

 

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

 

Annual energy demand

Lighting

152.9 kWh

Heating

7,567.6 kWh

Ventilation

2,433.6 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

6.03%  (0.43% standard variation)

Thermal comfort 1

10.5 h (always overheated)

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

The picture below demonstrates the dry resultant temperature and ambient temperature inside the drying room for a typical winter working day. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                 Ambient and cabin’s dry resultant temperature

 

It is shown that a dry resultant temperature about 20°C is maintained 24 hours during working days. Thus, the drying room of improved standard provides an effective environment for clothes drying.

 Back to Top

The subcontractor’s cabin is a 9.5m x 3m cabin with the following characteristics:

  • 3 occupants for 5 hours per day
  • 1 computer (7:00 –18:00)
  • 2 x 2kW heater and 5 x 58W lamps
  • Infiltration: 4ac/h (doors open)

 

Current situation: The following assumptions have been made.

·       Heating behaviour of occupants:

  • 7:00 - 9:00 both heaters on maximum power (2 x 2000W)
  • 9:00 - 18:00 both heaters on middle power (2 x 1250W)

Lighting behaviour of occupants:

  • 7:00 – 18:00 lights on

 

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

912 kWh

Heating

3965 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

24.34%  (30.58% standard variation)

Thermal comfort 1

2 h

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

 

Pictures below demonstrate the dry resultant temperature inside the subcontractor’s cabin for a typical winter day. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                      Ambient and cabin’s dry resultant temperature

 

It is demonstrated that the required dry resultant temperature of 20°C cannot be maintained. During a typical winter day the dry resultant temperature inside the subcontractor’s cabin will typically be below the required comfort level. Thus, discomfort will be experienced.

 

Proposed Situation: Following energy efficiency measures have been applied.

·         Improve insulation

  • 36W T5 tubular fluorescent lights
  • Occupancy sensor for lights
  • 1.5 kW heater with automatic temperature control (start time: 6:00)

 

The following assumptions have been made:

  • Doors mostly closed (1.5 ac/h)

Heating:

  • Heating control to maintain a dry bulb temperature of 20°C

Lighting:

  • 25 % less rating (HF control)

  • Lights 55% switched off (5h per day switched on)

The results shown in the tables below have been arrived from a combination of ESP-r simulations and calculations.

 

 

Annual energy demand

Lighting

191 kWh

Heating

1567 kWh

 

 

For a typical winter day (7:00 – 18:00)

Thermal percentage dissatisfied

10.69%  (18.12% standard variation)

Thermal comfort 1

10 h

1 Hours per day where the dry resultant temperature lies between 20°C and 22°C

 

 

Pictures below demonstrate the dry resultant temperature inside the subcontractor’s cabin for a typical winter day. The upper line shows the dry resultant temperature, the lower line shows the ambient temperature

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                           Ambient and cabin’s dry resultant temperature

 

It is shown that a dry resultant temperature above 20°C is maintained between 8:00 and 18:00. Thus, the cabin of improved standard provides a comfortable working environment for subcontractors.

 

 Back to Top

The following two tables summarise all results gained from the case study for:

  •          One contractor’s office

  •          The contractor’s canteen

  •          The contractor’s drying room

  •          One subcontractor’s cabin

 Energy Savings and Investments

 

Initial annual energy demand

kWh

Final annual energy demand

kWh

Energy Savings

%

Initial annual energy cost

£ 3

Final annual energy cost

£

Capital Investment

£

Payback Period

yrs

Office

 

 

 

 

 

 

 

Lighting

227

60

73.5

23

6

200

11.8

Heating

1235

471

61.9

124

47

130

1.7

Total

1462

531

63.7

147

53

330

3.5

Canteen

 

 

 

 

 

 

 

Lighting

2831

765

73

283

77

1050

5.1

Heating

4680

3550

24.1

468

355

520

4.6 A

Ventilation

-

780

-

-

78

615  

 

Total

7511

5095

32.1

751

510

2185

9.0

Drying room

 

 

 

 

 

 

 

Lighting

1019

153

85

102

15

410

4.7

Heating

22464

7568

66.3

2246

757

650

0.4

Ventilation

-

2434

-

-

234

320

 

Total

23483

10155

56.8

2348

1006

1380

1.0

Subcontractor’s Cabin

 

 

 

 

 

 

 

Lighting

912

191

79.1

91

19

200

2.8

Heating

3965

1567

60.5

397

157

260

1.1 B

Total

4877

1758

64

488

176

460

1.5 / 8.8 C

Notes:  1 based on 10 pence/kWh energy costs

A shorter payback period if ventilation is neglected

B no consideration of extra hire costs for well-insulated cabin

C considering an additional yearly hire charge of £260 for a well insulated cabin                             

 

 

Carbon Emissions and Thermal Comfort

 

Initial annual CO2 emissions

kg

Final annual CO2 emissions

kg a

Initial Percentage Dissatisfied

% b

Final Percentage dissatisfied

%

Initial period of

thermal comfort

hours b c

Final period of thermal comfort

hours

Office

1360

494

40.5

8.3

1  (9%)

10 (91%)

Canteen

6985

4738

52.6

13.8

½ (5%)

4 (36%)

Drying room

21839

9444

88.4

8.0

0 (0%)

10.5 (95%)

Subcontractor’s cabin

4536

1635

24.4 d

10.7

2 (18%)

10 (91%)

Notes:  a based on 0.93 kg/kWh

b during working hours of a typical winter day

c for a dry resultant temperature between 20°C -22°C

d however, 30.58% standard deviation 

 

Back to Top

Back


Home | Overview | Background | Project | Conclusions | Resources

This website is best viewed on Internet Explorer at 1024x768 resolution
Developed by Group 1- MSc Energy Systems & Environment year 2005/06
Webmaster:miguelcam_1@hotmail.com /Last updated: 07-May-2006
.