Home Overview Background Project Conclusions Resources


 

 

 

 

 

 

 

 

 

 

                    Improvements of Xscape Site demand

Back

Contents

 

        1         Introduction

        2         Objective

        3         Methodology

        4         Case Study

        5         Conclusion

        6         References

1. Introduction

This project will apply the methodology, outlined previously, to the construction village at Laing O’Rourke’s Xscape site. The construction village consists of 26 modular contractor’s cabin linked together over 2 storeys and 9 jackleg cabins used by subcontractors.

 

Contractor’s accommodation is constructed to current Building Regulations regarding their specification of insulation. It is however, notable that the subcontractor’s cabins are of an older model with poor insulation envelope.

 

The construction village consists of offices, meeting rooms, toilets, canteen, kitchen and a drying room for both contractors and subcontractors.

  

 Back to Top

2. Objectives

Our objectives are to demonstrate significant improvements for chosen areas of the Xscape site by applying the energy efficiency measures that were identified in the previous section. By applying the first step of our methodology, which is concerned with demand side management, to the Xscape site we will achieve improvements in the following areas:

1.       Energy Demand

2.       Thermal Comfort

3.       Environmental Impact

Further outcomes from the Xscape study will be:

1.       Investment costs

2.       Payback Periods

  

 Back to Top

3. Methodology

 

 Text Box: Study demand profile of Xscape site
Text Box: Select areas with high energy demand
Text Box: Select energy efficiency measures for each area
Text Box: Carry out analysis for proposed situation
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The first step of this study is to identify areas with a high energy demand. In these areas we will then apply a number of selected energy efficiency measures. In order to identify significant areas within the Xscape site, the accommodation layout, the power installed in every area, the quantity of a certain area as well as the periods of energy usage have been studied, considering the information obtained on the Demand Analysis of the Project Web Site.

§         Xscape contractor’s accommodation layout 

§         Power installed in every area 

§         Periods of energy usage

Then, by studying the complete construction village we have identified the following target areas:

 

 

 

 

            Offices                                  

 

 

 

 
 

            Canteen

 

                                          

 

 

 

 

Drying Room                                                           

 

 

 

 

 


           Subcontractor’s Cabins                                                      

 

 

 

 

 

It shall be mentioned that the Xscape site contains 13 contractor’s offices, one contractor’s canteen and drying room and 9 subcontractor’s cabins.

 

In the next step the appropriate energy efficiency measures are identified which shall be implemented in the selected areas. These measures have previously been summarised in our demand side study. The figure below shows the energy efficiency measures applied to each area.

 

 

Offices
• High frequency ballasts
• Daylight control system
• 1.5 kW heater with automatic control
Canteen
• High frequency ballasts
• Occupancy sensor for lights
• 1.5 kW heater with automatic control
• Ventilator (428m3/hr) with heat recovery and CO2 sensor
Drying Room
• High frequency ballasts
• Occupancy sensor for lights
• 1.5 kW heater with automatic control
• Ventilator with 157m3/hr with heat recovery and humidity sensor
Sub-contractor’s Cabins
• Improved insulation
• 36W T5 fluorescent lights
• Occupancy sensor for lights
• 1.5 kW heater with automatic control

 

The last step is to carry out an analysis for these areas using the selected measures in comparison to their current situation.

 

 Back to Top

4. Case study

In this case study we conduct an analysis for the chosen areas with the help of ESP-r. This is done by assessing our proposed situation in comparison with the current situation on the construction site. The proposed situation is based on implementing previously identified energy efficiency measures in the selected areas.

 

This case study is based on the actual room sizes occurring in the Xscape construction village and also takes into account the surrounding area of the various rooms as well as the working behaviour of all employees. Working hours are assumed to be 11 hours per day for 5 days a week and 52 weeks per year. The case study can be accessed via a link in the Demand Side part of the Project Web site.

 

 Back to Top

5. Results summary

In the following all results arrived from the case study are tabular or graphical listed for:

·         The 13 contractor’s offices

·         The contractor’s canteen

·         The contractor’s drying room

·         The 9 subcontractor’s cabins

The main results are listed in the table below.

 

 

 

Accommodation

Annual Energy Savings

£

Capital Investment

£

Payback Period

yrs

Avoided CO2 Emission kg/yr

Offices

 

 

 

 

Lighting

221

2600

11.8

 

Heating

1001

1690

1.7

 

Total

1222

4290

3.5

11,258

 

 

 

 

 

Canteen

 

 

 

 

Lighting

206

1050

5.1

 

Heating

113

520

4.6 A

 

Ventilation

-

615  

 

 

Total

241

2185

9.0

2,247

 

 

 

 

 

Drying room

 

 

 

 

Lighting

87

410

5

 

Heating

1489

650

0.4

 

Ventilation

-

320

-

 

Total

1342

1380

1.0

12,395

 

 

 

 

 

Subcontractor’s Cabins

 

 

 

 

Lighting

648

1800

2.8

 

Heating

2160

2340

1.1 B

 

Total

2808

4140

1.5 / 8.8 C

26,109

Note:

A shorter payback period in case of unventilated space

B no consideration of extra hire costs for well insulated cabin

C considering an additional yearly hire charge of £260 for a well insulated cabin

 

 

Furthermore, all results are shown in the following graphs.


 

 

 

 


 

                                                                                                                                                               

 

Text Box: kWh
Text Box: kg

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

                                                                                                                                                                

Text Box: yrs
Text Box: £
Text Box: %
Text Box: %

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

                                                                                                                                                                      

 

 

 

 

 

 

Notes:

 

1 Thermal comfort and thermal percentage dissatisfied are stated for a typical winter day

2 Thermal comfort: percentage of working hours with a dry resultant temperature 20°C – 22°C

3 There are two values on the Simple Payback Period for the Sub-contractor's. The longer payback was calculated taking into account the extra hiring charges of good insulated cabins while the shorter payback just assumed the company purchasing from new.  

 

 Back to Top

6. Conclusion

In conclusion the following goals have been achieved:

 

  1. Reduction of annual energy demand

  2. Reduction of annual energy cost

  3. Reduction of annual carbon emissions

  4. Improvement of thermal comfort

  5. Decreased number of dissatisfied employees

 

It has been demonstrated that the application of energy efficiency measures can lead, in the Xscape construction village, to energy savings between 32% and 64% depending on the target area.

 

This report indicates that, because of their high percentage of energy savings but relatively low payback periods, the contractor’s offices and the drying room are primary targets for implementing selected energy efficient lighting, heating and ventilation equipment. In case of the drying room the application of ventilators with heat recovery and humidity sensors will additionally provide an effective environment for clothes to dry and therefore solve a main problem faced on every construction site.

 

Changing the subcontractor’s cabin on the Xscape site by hiring well insulated cabins and applying selected heating and lighting measures requires a high initial investment. However, improving subcontractor’s accommodation will lead to a significant reduction in annual carbon emissions which will contribute towards achieving national targets and thus help to lead towards sustainable development.

 

Despite savings of energy and carbon emissions, by applying our methodology in the Xscape construction village the environmental comfort of all areas investigated will be enormously improved. This will lead in to a working environment where employees are able to work effectively due to the improved level of comfort.

 

 Back to Top

Back


Home | Overview | Background | Project | Conclusions | Resources

This website is best viewed on Internet Explorer at 1024x768 resolution
Developed by Group 1- MSc Energy Systems & Environment year 2005/06
Webmaster:miguelcam_1@hotmail.com /Last updated: 07-May-2006
.