Therefore, after calculating the
annual output for various models it was found that the proven
WT15000 seemed to be a more worthwhile
investment.
After making an exclusive study on above turbines with respect
to various aspect as described earlier we see that Proven WT
15000 was selected in this 15 kW rating category as it has
reasonably higher generation capability due to greater swept
area, being less expensive, and being
known to be fairly robust requiring a low maintenance
regime meant that upon comparing the
turbines of the same size the Proven WT
was a clear favourite.
Back to Top
Hence, based on the power output from each 15 kW turbine and
depending upon the total demand on the construction site it is possible to calculate the number of turbines required for installation. One
further factor which has to be considered
is the type of storage medium to be used, such as a battery
banks, or connecting the excess supply to the grid or using it
for direct heating applications, the above choice entirely
depends upon the site conditions. The first strategy which could
be considered is by just using a single 15 kW turbine to meet
the reasonable portion of the total loads during the morning
hours and during the night the energy produced could be used for
supplying energy for drying the clothes in the drying room. The
second strategy is to install the required number of turbine to
meet the total demand in the site. Upon considering the above
two strategy it can be seen that
the first option proves to be more
advantageous in terms of feasibility in supply, having low risk
involved due to less investment cost due to the reduction in the
cost of battery bank for storage capacity.
The total lifetime cost was determined by estimating the annual
loan repayments, overall operation and maintenance expenses,
property tax and insurance for the design lifetime and expenses
for reserving equipment parts and others in store for unexpected
breakdown. This total lifetime cost was then used to estimate
the cost per kWh of electricity generated from the turbines. The
economic viability of a small wind power system depends to a
large extent on the generating costs and the associated market
value of wind energy Capital cost, financial cost, operating and
maintenance costs, turbine availability, energy efficiency, life
time of turbine and site wind regime constitute the total
generating costs. On the other hand, environmental benefits
which comprise emissions reduction (CO2 savings) and
reduced fossil fuel use, together with fuel savings and capital
savings make up the associated market value of wind energy.
3.5.1 Capital Costs
These are the total cost involved including the material cost,
foundation cost, and installation cost for the turbine.
Generally, wind turbine installed costs are normalized to cost
per unit of rotor area or cost per rated kW.
The price of Proven WT 15 kW turbines comes up depending upon
the type of connection associated with it.
|
Wind Turbine System with |
Basic Cost (£) |
1. |
Grid Connected |
39,000 |
2. |
Battery Charging |
46,500 |
Source: Proven Energy
The reason behind the price difference between two connections,
are due to the extra cost associated with putting up batteries
for storing the produced energy. Further the connection to the
grid normally takes place at <16 amps/phase.
3.5.2 Financing Costs
As
most wind power projects are capital intensive. Usually most
developers make a down payment and finance the rest of the
project with a loan obtained from the financial institution, in
most cases a bank loan. Then in long term interest has to be
paid for the money borrowed from the bank.
3.5.3 Operation and Maintenance Costs
As
the turbine contains more moving parts, hence it requires a
considerable maintenance to be done, for an efficient running.
It is considered that the during the early years the maintenance
cost are between 1.5% and 3% of the turbine cost but increase
with time as the turbines get older.
3.5.4 Payback
The detailed analysis done regarding the payback shows that with
good wind resource at the installed site, the payback for a 15kW
wind turbine will normally be about 10 years. Further with the
usage of additional storage facilities like battery would
increase an additional payback period of 13 years.
Back to Top
A battery charging system provides us with a continuous
uninterrupted power supply for our applications via an inverter
which makes the power from the turbine usable. According to
manufactures recommendation 48V DC battery storage can be used
for storing the generated electricity. This is then converted
into AC by means of an inverter before we are capable of using
it for our utilities. The number of batteries required for a
particular installation depends upon how long we need to have
electricity supply when there is no wind. Normally the battery
storage is planned for storing electricity for about say one or
two weeks. Hence the cost of each battery varies depending upon
its storage capacity.
A general idea about the cost of batteries and inverters are given
below in the table as
The cost of 48V Varta Lead Acid Battery (Tubular Plate, Flooded
cell) depends on the storage capacity in Ampere hours
No |
Ampere hours(Ah) |
Cost (£) |
1. |
470 |
2962 |
2. |
785 |
4631 |
3. |
1250 |
7178 |
The selection of a medium capacity storage battery of 48V, 785Ah
could be considered based on the continuous demand required from
the construction site.
Similarly the below is the price list for the inverters for a
typical SMA Windy boy inverter model of the following capacity
No |
Rating (kW) |
Cost (£) |
1. |
2.5 |
1338 |
2. |
3 |
1453 |
3. |
6 |
2527 |
Back to Top
The UK government providers funding through various means towards
the implementation of various renewable energy sources through
various scheme means such as
1.
Low carbon building programme.
2.
Green energy trust Scottish power.
3.
Green energy fund.
4.
Leader plus programme.
Back to Top
The supply results from this project will tell us about the
expected amount of carbon dioxide savings depending upon the
portion of electricity generated from the turbine to the use of
diesel generator or grid connected electricity supply. The
installation of the above wind turbine will reduce the connected
load on the generator and the grid thereby we are able to save a
considerable amount of Carbon Dioxide emissions.
Back to Top
Hence upon analyzing various turbine model for a same wind
pattern but for a different hub height it is found Proven WT
15000 was able to produce about 5626.2 kWh/month at hub height
of 30m(these values vary highly depending upon the prevailing
wind condition and hence the manufacturers recommendation for
annual energy production has to be considered)
Device |
Size |
Investment
( ₤ ) |
Payback
( years ) |
Cost
( p/kWh ) |
CO2 emissions
( kg/kWh )
|
Wind turbine+ Battery + Inverter |
15 kW
48 V DC |
46,500 |
13 |
8.8 |
* |
Wind turbine+ grid connected
|
15 kW |
39,000 |
11 |
7.3 |
* |
* Wind turbine has no Carbon Dioxide emissions but savings.
Back to Top
It is reasonable to conclude that from
the analysis shown above considering exclusively
small scale wind turbines, we see that the 15kW Proven turbine
is the optimum selection, after considering various factors for
its selection process. Hence a single turbine is capable of
meeting the current lighting demand with an excess supply which
can be used for direct heating or storage purposes. A single
15kW proves to be more economical to meet the lighting demand or
we need to install 3 turbines which considerably increases the
investment cost and raise the risk involved in it. The normal
payback estimated is between 10-15 years.
This initiative will give more long term result proving the
corporate social responsibility of the firm for the investors
and the sustainability effort taken towards the CO2
reduction and from the environmental point of view.
Back to Top
1.
Small Scale Wind Turbines: Alternative Power Supply Option
for Construction Sites,
--By Kenneth Edem Agbeko
2.
http://www.windustry.com/basics/03-knowwind.htm
3.
http://www.wind.appstate.edu/photogallery/swindgallery.php
Back to Top
 |