| 
				
				Therefore, after calculating the 
				annual output for various models it was found that the proven 
				WT15000 seemed to be a more worthwhile
				investment. 
				  
				
				After making an exclusive study on above turbines with respect 
				to various aspect as described earlier we see that Proven WT 
				15000 was selected in this 15 kW rating category as it has 
				reasonably higher generation capability due to greater swept 
				area, being less expensive, and being 
				known to be fairly robust requiring a low maintenance 
				regime meant that upon comparing the 
				turbines of the same size the Proven WT 
				was a clear favourite. 
				  
				
				
				 Back to Top 
				Hence, based on the power output from each 15 kW turbine and 
				depending upon the total demand on the construction site it is possible to calculate the number of turbines required for installation. One 
				further factor which has to be considered 
				is the type of storage medium to be used, such as a battery 
				banks, or connecting the excess supply to the grid or using it 
				for direct heating applications, the above choice entirely 
				depends upon the site conditions. The first strategy which could 
				be considered is by just using a single 15 kW turbine to meet 
				the reasonable portion of the total loads during the morning 
				hours and during the night the energy produced could be used for 
				supplying energy for drying the clothes in the drying room. The 
				second strategy is to install the required number of turbine to 
				meet the total demand in the site. Upon considering the above 
				two strategy it can be seen that 
				the first option proves to be more 
				advantageous in terms of feasibility in supply, having low risk 
				involved due to less investment cost due to the reduction in the 
				cost of battery bank for storage capacity.   
				  
				
				The total lifetime cost was determined by estimating the annual 
				loan repayments, overall operation and maintenance expenses, 
				property tax and insurance for the design lifetime and expenses 
				for reserving equipment parts and others in store for unexpected 
				breakdown. This total lifetime cost was then used to estimate 
				the cost per kWh of electricity generated from the turbines. The 
				economic viability of a small wind power system depends to a 
				large extent on the generating costs and the associated market 
				value of wind energy Capital cost, financial cost, operating and 
				maintenance costs, turbine availability, energy efficiency, life 
				time of turbine and site wind regime constitute the total 
				generating costs. On the other hand, environmental benefits 
				which comprise emissions reduction (CO2 savings) and 
				reduced fossil fuel use, together with fuel savings and capital 
				savings make up the associated market value of wind energy. 
				  
				  
				
				3.5.1 Capital Costs 
				
				These are the total cost involved including the material cost, 
				foundation cost, and installation cost for the turbine. 
				Generally, wind turbine installed costs are normalized to cost 
				per unit of rotor area or cost per rated kW.  
				  
				
				The price of Proven WT 15 kW turbines comes up depending upon 
				the type of connection associated with it. 
				  
					
						
							| 
							  | 
							
							
							Wind Turbine System with | 
							
							
							Basic Cost (£) |  
							| 
							1. | 
							Grid Connected | 
							39,000 |  
							| 
							2. | 
							
							Battery Charging | 
							46,500 |  
				
				Source: Proven Energy 
				
				The reason behind the price difference between two connections, 
				are due to the extra cost associated with putting up batteries 
				for storing the produced energy. Further the connection to the 
				grid normally takes place at <16 amps/phase. 
				
				  
				
				3.5.2 Financing Costs 
				As 
				most wind power projects are capital intensive. Usually most 
				developers make a down payment and finance the rest of the 
				project with a loan obtained from the financial institution, in 
				most cases a bank loan. Then in long term interest has to be 
				paid for the money borrowed from the bank. 
				  
				
				3.5.3 Operation and Maintenance Costs 
				As 
				the turbine contains more moving parts, hence it requires a 
				considerable maintenance to be done, for an efficient running. 
				It is considered that the during the early years the maintenance 
				cost are between 1.5% and 3% of the turbine cost but increase 
				with time as the turbines get older. 
				  
				
				3.5.4 Payback 
				
				The detailed analysis done regarding the payback shows that with 
				good wind resource at the installed site, the payback for a 15kW 
				wind turbine will normally be about 10 years. Further with the 
				usage of additional storage facilities like battery would 
				increase an additional payback period of 13 years. 
				  
				
				
				 Back to Top 
				A battery charging system provides us with a continuous 
				uninterrupted power supply for our applications via an inverter 
				which makes the power from the turbine usable. According to 
				manufactures recommendation 48V DC battery storage can be used 
				for storing the generated electricity. This is then converted 
				into AC by means of an inverter before we are capable of using 
				it for our utilities. The number of batteries required for a 
				particular installation depends upon how long we need to have 
				electricity supply when there is no wind. Normally the battery 
				storage is planned for storing electricity for about say one or 
				two weeks. Hence the cost of each battery varies depending upon 
				its storage capacity.  
				A general idea about the cost of batteries and inverters are given 
				below in the table as  
				The cost of 48V Varta Lead Acid Battery (Tubular Plate, Flooded 
				cell) depends on the storage capacity in Ampere hours 
				 
				
				
				  
					
						
							| 
							
							
							No | 
							
							
							Ampere hours(Ah) | 
							
							
							Cost (£) |  
							| 
							1. | 
							470 | 
							2962 |  
							| 
							2. | 
							785 | 
							4631 |  
							| 
							3. | 
							1250 | 
							      
							7178 |  
				The selection of a medium capacity storage battery of 48V, 785Ah 
				could be considered based on the continuous demand required from 
				the construction site. 
				  
				Similarly the below is the price list for the inverters for a 
				typical SMA Windy boy inverter model of the following capacity 
					
						
							| 
							
							
							No | 
							
							
							Rating (kW) | 
							
							
							Cost (£) |  
							| 
							1. | 
							2.5 | 
							1338 |  
							| 
							2. | 
							3 | 
							1453 |  
							| 
							3. | 
							6 | 
							2527 |    
				 Back to Top 
				The UK government providers funding through various means towards 
				the implementation of various renewable energy sources through 
				various scheme means such as 
				  
				
				1.                  
				
				Low carbon building programme. 
				
				2.                  
				
				Green energy trust Scottish power. 
				
				3.                  
				
				Green energy fund. 
				
				4.                  
				
				Leader plus programme. 
				  
				Back to Top  
				
				The supply results from this project will tell us about the 
				expected amount of carbon dioxide savings depending upon the 
				portion of electricity generated from the turbine to the use of 
				diesel generator or grid connected electricity supply. The 
				installation of the above wind turbine will reduce the connected 
				load on the generator and the grid thereby we are able to save a 
				considerable amount of Carbon Dioxide emissions.   
				  
				
				 Back to Top 
				
				Hence upon analyzing various turbine model for a same wind 
				pattern but for a different hub height it is found Proven WT 
				15000 was able to produce about 5626.2 kWh/month at hub height 
				of 30m(these values vary highly depending upon the prevailing 
				wind condition and hence the manufacturers recommendation for 
				annual energy production has to be considered)   
					
						| 
						
						
						
						Device | 
						
						
						Size | 
						
						
						Investment 
						
						
						( ₤ ) | 
						
						
						Payback 
						
						
						( years ) | 
						
						
						Cost 
						
						
						( p/kWh ) | 
						
						
						CO2 emissions 
						
						
						( kg/kWh ) 
						
						
						  |  
						| 
						
						
						Wind turbine+ Battery + Inverter | 
						
						15 kW 
						
						48 V DC | 
						
						46,500 | 
						
						13 | 
						
						8.8 | 
						
						* |  
						| 
						
						
						Wind turbine+ grid connected 
						  | 
						
						15 kW | 
						
						39,000 | 
						
						11 | 
						
						7.3 | 
						
						* |  
				
				  
				
				* Wind turbine has no Carbon Dioxide emissions but savings. 
				  Back to Top  
				
				It is reasonable to conclude that from 
				the analysis shown above considering exclusively 
				small scale wind turbines, we see that the 15kW Proven turbine 
				is the optimum selection, after considering various factors for 
				its selection process.  Hence a single turbine is capable of 
				meeting the current lighting demand with an excess supply which 
				can be used for direct heating or storage purposes. A single 
				15kW proves to be more economical to meet the lighting demand or 
				we need to install 3 turbines which considerably increases the 
				investment cost and raise the risk involved in it. The normal 
				payback estimated is between 10-15 years.   
				
				This initiative will give more long term result proving the 
				corporate social responsibility of the firm for the investors 
				and the sustainability effort taken towards the CO2 
				reduction and from the environmental point of view. 
				  
				  
				 Back to Top  
				
				1.                  
				
				Small Scale Wind Turbines: Alternative Power Supply Option 
				for Construction Sites, 
				--By Kenneth Edem Agbeko  
				
				2.                  
				
				
				
				http://www.windustry.com/basics/03-knowwind.htm 
				
				3.                  
				
				
				
				http://www.wind.appstate.edu/photogallery/swindgallery.php 
				  Back to Top 
			
			 |