Week 1
· Introduction
to group members.
· Met with
industrial contact - Department of Architecture (University of Strathclyde).
· Rottenrow
Site under consideration for case study.
· Review of
possible energy efficient technologies for use in case study.
· Decision
to go ahead with supply/demand matching at Rottenrow site (using Merit).
· Decision
to go ahead with thermal modelling of Rottenrow site (using ESP-r).
· First
Critical Review.
· Start made
on Web-Page Development.
· Following
Critical Review advised to investigate Case Studies of existing Zero/Low
emissions buildings to fully appreciate the current state of the art.
· Case
Studies to be reviewed identified.
· Case
studies delegated to group members.
· Second
Critical Review.
· Web Page updated.
· Reviewed
Sick Building Syndrome.
· Defined
the direction of our Project which is to develop a methodology for selecting
technologies to incorporate within building design.
· During a brainstorming
session developed our methodology for the selection of technologies/materials
by outlining a selection criteria.
· Responsibilities within group delegated.
· Web Page
updated.
· Reviewed
the common practice Building Design Process.
· Discovered
no methodology currently existing for selection of technologies/materials for
use within buildings which strengthened our case for developing a selection
criteria.
· Selection
criteria for selection of materials/technologies under further development.
·
ESP-r Modelling of Rottenrow Site commenced.
· Preparation
of information for third Critical Review.
· Web Page
updated.
· Initial
study of lifecycle analysis undertaken.
· Selection
criteria for selection of materials/technologies under further development.
· ESP-r
modelling continuing.
· Third
Critical Review.
· Web Page
updated.
· Abandoned
high level selection tool as was impractical due to high degree of complexity.
· Altered
strategy to developing a more comprehensive reference type selection tool.
· ESP-r
construction model completed. Building Electrical and Heating demands
calculated on paper.
· Web Page
updated.
· Supply/Demand
matching on Merit commenced.
· Reference
tool being updated with information.
· Visited
HLM architects to gain industrial perspective on selection tool.
· Web Page
Updated.
· Fourth
Critical Review.
· Reference
tool near completion.
· Merit
Supply/Demand matching near completion.
· ESP-r
model attributed for simulation.
· On going
work on selection tool.
·
Supply/Demand Matching completed.
·
ESP-r simulations underway.
·
Preparation for final presentation underway.
·
Web Page updated.
·
ESP-r Simulation complete.
·
Quantatative Analysis.
·
On-going work on final presentation and web Page.
·
Web Page Completed.
· Preparations for final presentation.