Navigation

  1. Pipes Under Roof
  2. Pipes On Roof
  3. Vertical Borehole
  4. Horizontal
  5. Air Source
  6. Summary

Heat Source Extraction Options

First Option: Pipes under roof

Technical Appraisal

The warm air flowing around the underground station due to train movement will move up and fill all of the spaces. By laying pipes on top of the station's false ceiling, low grade energy could be extracted.
A manual temperature measurement was taken and it showed that the ambient temperature in the underground station was between 13 and 14 oC.
The material of the false roofing was unknown at the time the study was completed therefore it was assumed to be either cladded metal or plastic based material.
To support the pipes that are being laid on top of the ceiling, a tubular mesh would need to be constructed. Alternatively the pipe could be held via a plate, that is, flexibly attached to the pipes and rigidly bolted to the side walls. The final choice would be made after an agreement had been reached between the contractor and Strathclyde Passenger Transport (SPT).

To calculate the amount of extractable heat several factors were examined: pipe length available, flow of working fluid and ambient temperature around the pipe. All the thermal resistances must be taken into account in determining the temperature drop.
For the amount of heat extractable using 121 m2 area of pipe we could get less than 2 kW energy.
This option has a significant disadvantage due to the turbulent air and the fact that the station is not an enclosed space. Therefore, warm and cold air can move freely and the low grade energy lost due to the lack of insulation.

Second Option: Pipes on roof

Technical Appraisal

This option is similar to the first, however the warm air has to overcome more thermal resistance particularly from the roof which is made of corrugated cladded aluminium. The area available for heat extraction is 96 m2. Above the roof there will be a raised decking built to conceal the roof from any unauthorised access.
In this method, the pipes would be suspended on top of the roof. Some structural means of holding these pipes must be designed, as mentioned in the first option.

From calculation, the energy extractable is less than 1 kW. This is the least amount of energy extractable from all the options.


Third Option: Vertical type borehole

Technical Appraisal

Below is a map of average ground temperatures across the UK.

The third option is known as Vertical type closed loop ground source heat extraction scheme. The area available around the Underground station roof made possible 3 boreholes. 1 borehole could extract around 12 to 21 kW of heat from the earth depending on the depth. From the map below it can be seen that in Glasgow at a depth of 50 m, the temperature is approx. 13 oC.

Vertical trenches must be built as shown in the picture (in heavy black lines), with the pipe surrounded by grouting material to help increase the efficiency. With the area available, only a single row of trenches is suitable. Typically a borehole must be made 1.5 m away from the nearest wall, and the distance from 1 borehole to another should be 5 m. The figures quoted take into account the borehole diametrical size plus the neccessary grout space around the boreholes.
Borehole drilling is costly taking up £500 to £2000 per borehole. The major advantage of borehole type energy extraction, is that it makes the most of the area available.


Fourth Option: Horizontal type

Technical Appraisal

Laying the pipe horizontally may also be considered for energy extraction. A trench would be dug to accommodate the pipes as shown below and this scheme is the optimum layout possible for the Horizontal type. The trench would need to be 1.8 m deep with the pipes laid 1.8 m from ground zero. Allow 0.5 m from the side wall and 0.6 m between pipes horizontally. For the combination proposed an extra 0.4 m in parallel-vertical depth would be necessary to add a parallel pipe. The energy extracted is in the region of 35 to 55 m per kW. This is approximately 1.5 to 2.4 kW extractable heat.

To increase the area available for heat extraction using the horizontal layout, slinkies could be used in place of a normal pipe. Slinkies are pipes which are rolled as shown and connected to one another. This design would maximise the surface available for heat extraction. A similar trench would be dug to accommodate the pipes as shown above. The trench must be dug 1.8 m deep and the pipe laid 1.8 m from ground zero, allowing for a clearance of 0.5 m from the side. With slinkies, the trenches must be postitioned 5 m apart therefore for this site only a single trench is possible. The potential energy extracted is 30m per kW, approximately 3 kW extractable heat.

Fifth Option: Air source heat pump

The last option looked at for heat extraction is to directly move the warm air from the underground station via a blower pump fitted on top of the station’s ceiling. The warm air would then be sent to the heat exchanger part of the Heat pump system located within the building. Using this method, the warm air transfer duct must be properly insulated to ensure no significant heat loss before reaching the heat exchanger. The amount of energy transferable depends upon the sizing of the heat pump and the optimum efficiency balance that the extractable heat can provide.
Relevant Material Information
Option 1 & 2 – The pipes would be made of copper, size around 32 mm OD
Option 3, 4, 5 – Pipes are plastic
Relevant Material costing refer to: http://www.kensaengineering.com

Summary of Heat Extraction Options

The table shows a comparison of the energy extracted using the 6 proposals. As shown, the pipe buried vertical option can provide the highest low grade energy extractable within the available area, however this option has the highest cost weighting which is not so good. As mentioned earlier, this option could have a low cost weighting if good planning were carried out during the construction phase.
The last proposal, the air source, appears to be a good way of implementing a heat pump, however the warm air supply may not be constant as the underground only operates for approx. 16 hours each day.
To conclude, from the heat extraction study, we found that 2 proposals were suitable; the vertical borehole and air source. The air source option is particular to this site due to the presence of the underground system whereas the vertical borehole option could easily be transferred to a wide selection of sites.