Our
first consideration about an offshore wind farm is a fact!
Literature
and critical review about the topic
We
decide to focus as soon as possible in order to have time to develop
the project
Third
week
Change of plans after
the last crit
The topic of offshore
wind farm was not a good choice because it was similar as a topic in
the previous year
Everything from the
beginning again!
We are not very creative
of generating ideas and the brainstorming session didn’t help us very
much
Forth
week
After a discussion
with Professor Clarke we considered some other ideas
We decided that Distributed
Generation is an interesting
area and we should develop a project for this area
We started thinking
about the economical, environmental and social aspects of our project
Literature and critical
review about the topic of Distributed Generation
We discussed our new
topic with Dr S. Jovanovic and he agreed for this project
This was a crit week.
We presented the basic concept of our project but there were some uncertainties
in our general concepts. It was still complicated
Fifth week
We tried to define our objectives and
our base line
We try to focus to more technical details
We decided to focus to the North West
of Scotland because of the potential of renewable sources and the weakness
of the electricity grid in that area
Collecting information
for the Hydro and Wind potential in the area and also for the Demand (domestic, non-domestic customers, etc.)
Sixth
week
Follow
the plan of the previous week
We
have the first results from our calculations about the demand and the
Hydro and Wind potential
We
decided to apply distributed generation by covering the base load of
the demand
The
crit did not go well. We must redefine some aspects of our project.
They are not very optimistic about the objectives and the deliverables
of our study.
Seventh
week
We got into deep thinking
about what we are doing and how we could be more clear about our objectives
and also our contribution
According to our calculations
a small-hydro power plant will be the best solution for meeting the
demand
Studying the technical
details of the small-hydro distributed generation power plant for our
case study
Additionally, the barrier
of matching and dispatching the supply to the demand was decided to
be solved by developing a program in LabView environment
Eighth
week
We
started thinking about the layout of the web-site
Continuing
studying the technical details of the small-hydro distributed generation
power plant for our case study
Starting
developing the program in LabView
Ninth
week
Completing
the study for the technical details of the small-hydro distributed generation
power plant for our case study
Thinking
of how and with what order we are going to present the work (demand
and supply profiles, technical details of the plant, economic analysis,
etc.) we finished until then at the web-site
The
program in LabView is in a good progress
We
had a bad crit because we tried to show all of our work with a lot details
and not to explain from the results the benefits of this work
Tenth
week
The
program of LabView has been finished
Adding
our latest work at the web-site
Constructing
the rest texts (introduction, conclusions, etc.) for the web-site
Eleventh
week
We
started thinking of what is more important to be presented at the final
presentation
Preparation
of the slides which will be presented at the final presentation