Week Five (23/02/98 to 01/03/98)

Supervisory Details

Comments on presentation: Are we selling ourselves short? Could we involve more items in the project? Team felt that this could be opening Pandora’s Box.


Work in Progress

Scottish Power came up with half hourly data for the main in-comer sub station for the University for the last quarter 1997, no response regarding Eaglesham. Scottish Gas contacted ut it does not look like that any data will be made available for either site. Scottish Gas log the John St. High Pressure meter daily, difficult to attach logger due to their logger and safety requirements. University electricity meters in general old and not amenable to logging, main meter in John St. is sealed by S.P. as it is their cable entering it - so manual recording or Video ?(investigate) . Decide to extend data gathering portion of project, see below.
Members of the group attended the second HTML course conducted by CAP - most useful.


Agenda For Next Week

Chase up Scottish Power/Gas re:data
Set up monitoring of John St. meter - Video (see Cameron Johnston)
Confirm proposal

Time Chart 2


Back Front Forward